Rafter system of a hanging type of a gable roof. How to make a gable roof with your own hands. The main elements of the pitched roof system

During the construction of private houses, the roof is most often made gable. There are reasons for this. First, it is reliable. Handles wind and snow loads well. The second - it is compatible with any roofing. The third is relatively inexpensive. The fourth is a simple design that is difficult to spoil. Fifth - it looks attractive. All this, and also the fact that a do-it-yourself gable roof is built without special knowledge, determines its popularity.

Do-it-yourself assembled gable roof ready for installation roofing

Step-by-step installation of a gable roof

As you saw above, there are a lot of truss systems. Accordingly, when assembling each has its own characteristics, but in general order same. It is necessary to say about the general step: pre-drying and processing of wood. This step is required if you bought fresh lumber, not dried.

The use of raw wood of natural moisture in the construction of the roof will lead to problems: the beams will bend, they will dry out, the geometry will change. All this will lead to tension points and at the slightest sign of overload (lots of snow, strong wind or rain) negative processes will begin. Their elimination is a complex and costly undertaking. Therefore, either buy dry wood (no more than 20%, ideally chamber drying 8-12%), or buy material a couple of months in advance, stack in ventilated stacks. After that, treat with the necessary impregnations (from fungal attack and to reduce flammability) and only after that use it in the installation of the truss system.

Timber must be dried in ventilated stacks. To do this, they are laid in short pieces of boards. They are placed a meter from the edges and further through the meter. Spacers must be installed under the bottom

We will talk about the main stages of assembly, about how to make a gable roof with your own hands in this section.

Mauerlat

The assembly of the truss system begins gable roof from the installation of the Mauerlat. It must be set strictly horizontally, therefore, before starting installation, the horizontalness of the wall to which it is attached is carefully checked, if necessary, it is leveled cement mortar. You can continue work after the solution gains 50% strength.

Depending on the system, this is a beam with a section of 150 * 150 mm or a board with dimensions of 50 * 150 mm. It is attached to the top row of masonry walls. If the house is wooden, its role is played by the upper crown. If the walls are made of light building blocks - foam concrete or aerated concrete and others - their rigidity is not enough to redistribute the load. In this case, a reinforced concrete belt is made over the last row of masonry, into which embedded fasteners are embedded - wire or studs. A bar or board is then mounted on them.

There are several ways to connect walls and Mauerlat:

  • In the masonry (in the reinforced concrete belt) a smooth rolled wire of large diameter is fixed (two ends stick up). Holes are then made in the board in the necessary places, into which the wire is threaded. She then twists and bends.
  • Studs with a diameter of at least 12 mm are immured in the wall. Under them, holes are made in the Mauerlat, a beam / board is placed) and tightened with nuts with wide washers.
  • Aligning the beam or board along the outer or inner edge of the wall, take a drill with a diameter of 12 mm, make holes for the anchor bolts. They (the same diameter of 12 mm) are hammered to the very hat, then tightened with a key.

The distance between the studs (wire) should not be more than 120 cm. Cut-off waterproofing must be laid on the wall (belt) under the Mauerlat. It can be rolled roofing felt or waterproofing in two layers, it can be smeared with bituminous mastic.

Rafter installation

There are more than a dozen types of gable roof truss systems. First of all, you need to choose what yours will look like. Further, in order to make it easier to work, a template is made from thin boards for all cuts, cuts and other similar details. To do this, you may need to assemble the first form on the roof, and then make templates for the finished one.

The assembly order depends on the type of truss system. If the rafters are layered, they are installed gradually, assembling from the elements directly on the roof. In this case, it is convenient if the beams of the ceiling are laid and, if possible, the draft flooring of the attic or attic.

In systems with hanging rafters, a farm is assembled on the ground - a ready-made triangle of puffs and rafter legs with all the required struts, racks. The required number of farms is assembled at once. Then they are lifted to the roof, placed vertically there and attached to the Mauerlat.

On the one hand, this is convenient - it is easier to work on the ground, with a high assembly speed, the accuracy is high: one farm is not much different from the other, which simplifies the procedure. But it can be difficult to raise finished trusses, especially for large buildings. To make this easier, two inclined boards are installed, which at one end rest against the ground, and the other sticks out a little above the wall. Farms are brought closer to this “lift”, one by one they are installed below, ropes are tied and pulled along the boards to the roof. In the absence of a winch or crane, this is the most acceptable method.

The assembly of rafters requires certain knowledge: how and in what order to mount them, how to mark and make cuts. See the video for the assembly of one of the schemes with a headstock.

Assembly order of the truss system


Everything, the do-it-yourself gable roof is assembled and ready for installation of roofing material.

The process of installing the rafters itself raises enough questions, but there are many ways and it is impossible to tell about them all. See one of them in the video. The system is large and went up to the roof in parts, and there it was already assembled into a single structure. It is convenient for large houses.

Features of the installation of the truss system of a wooden house

difference wooden houses consists in the fact that the frame shrinks, and this leads to a change in the geometry of the truss system. If the elements are fixed rigidly, the roof may fall apart. Therefore, the mounts are made floating. There are special sliding fasteners, which in this case attach the rafters to the upper crown and to the girders, if any (see photo).

In order for the rafter to move freely during shrinkage, its long part is fixed strictly parallel to its edge, and the support is placed strictly perpendicular. If necessary, a platform is cut out under it. Mark the mount so that the hook is in the lowest position or near it. They are mounted on special self-tapping screws that come with the kit (ordinary ones do not fit). If the installation is done on a log, so that the rafter leg does not slip along it, a semicircular hole is cut out in the lower part, on which it will rest.

Such fasteners are sold on any construction market, it is called "slippery". How to attach the slippery to the timber, see the video.

Video on assembling and installing a gable roof truss system

Building a gable roof with your own hands is not easy: there are a lot of subtleties and nuances, there are different ways fixings, extensions. Describing them in words is a thankless task. This is the case when it is better to see. Below is a selection of videos that you might find useful.

Video report on how a gable roof is made

The story of the owner of the house about the stages of construction. There are interesting technical points that may be useful.

Two types of rafter connection: rigid and sliding

Video about the two most problematic types of connections.

How to determine the angle of the rafters

Full video report on the assembly of the truss system

This movie is just under an hour long, but the entire process is shown from start to finish with plenty of detail. The roof is placed on, but when installed on buildings of a different type (except for wooden houses), there is no difference.

Rafters perform a number of significant roofing functions. They set the configuration of the future roof, perceive atmospheric loads, and hold the material. Among the rafter duties are the formation of even planes for laying the coating and providing space for the components of the roofing pie.

In order for such a valuable part of the roof to flawlessly cope with the listed tasks, information about the rules and principles of its construction is needed. The information is useful both for those who are building a gable roof truss system with their own hands, and for those who decide to resort to the services of a hired team of builders.

In device roof frame For pitched roofs using wooden and metal beams. The starting material for the first option is a board, log, timber.

The second is constructed from rolled metal: channel, profile pipe, I-beam, corner. There are combined structures with steel most loaded parts and wood elements in less critical areas.

In addition to the "iron" strength, the metal has a lot of disadvantages. These include heat engineering qualities that do not satisfy the owners of residential buildings. Disappointing need for the use of welded joints. Most often, industrial buildings are equipped with steel rafters, less often private change houses assembled from metal modules.

In the case of self-construction of truss structures for private houses, wood is a priority. It is easy to work with it, it is lighter, “warmer”, more attractive in terms of environmental criteria. In addition, nodal connections do not require a welding machine and welder skills.

Rafters - a fundamental element

The main "player" of the frame for the construction of the roof is the rafter, among the roofers called the rafter leg. Beds, braces, headstocks, girders, puffs, even Mauerlat may or may not be used depending on the architectural complexity and dimensions of the roof.

The rafters used in the construction of the gable roof frame are divided into:

  • Layered rafter legs, both heels of which have reliable structural supports under them. The lower edge of the layered rafter rests on the Mauerlat or on the ceiling crown of the log house. The support for the upper edge can be a mirror analogue of an adjacent rafter or a run, which is a beam horizontally laid under the ridge. In the first case, the truss system is called spacer, in the second, non-spacer.
  • hanging rafters, the top of which rests against each other, and the bottom is based on an additional beam - puff. The latter connects the two lower heels of adjacent rafter legs, resulting in a triangular module called a truss truss. The tightening dampens the tensile processes, so that only a vertically directed load acts on the walls. The design with hanging rafters, although it is spacer, does not transfer the spacer itself to the walls.

In accordance with the technological specifics of the rafter legs, the structures constructed from them are divided into layered and hanging. For structural stability, they are equipped with struts and additional racks.

For the arrangement of supports for the top of the layered rafters, beds and girders are mounted. In reality, the truss structure is much more complicated than the elementary patterns described.

Note that the formation of a gable roof frame can generally be carried out without roof structure. In such situations, the alleged planes of the slopes are formed by slegs - beams laid directly on the bearing gables.

However, we are now specifically interested in the device of the gable roof truss system, and it can involve either hanging or layered rafters, or a combination of both types.

Subtleties of fastening rafter legs

The rafter system is fastened to brick, foam concrete, aerated concrete walls through the mauerlat, which in turn is fixed with anchors.

Between the Mauerlat, which is wooden frame, and with walls made of these materials, a waterproofing layer of roofing material, waterproofing, etc. is mandatory laid.

The top of the brick walls is sometimes specially laid out so that something like a low parapet is obtained along the outer perimeter. So it is necessary that the Mauerlat placed inside the parapet and the walls do not burst the rafter legs.

The rafters of the frame of the roofs of wooden houses rest on the upper crown or on the ceiling beams. The connection in all cases is made by cutting and duplicated with nails, bolts, metal or wooden plates.

How to do without furious calculations?

It is highly desirable that the cross section and linear dimensions of the wooden beams be determined by the project. The designer will give clear calculation justifications for the geometric parameters of the board or beam, taking into account the entire range of loads and weather conditions. If available home master there is no design development, his path lies on the construction site of a house with a similar roof structure.

You can ignore the number of storeys of the building under construction. It is easier and more correct to find out the required dimensions from the foreman than to find them out from the owners of a shaky unauthorized construction. After all, the foreman is in the hands of documentation with a clear calculation of the loads per 1 m² of roof in a particular region.

The installation step of the rafters determines the type and weight of the roofing. The heavier it is, the smaller the distance between the rafter legs should be. For laying clay tiles, for example, the optimal distance between the rafters will be 0.6-0.7 m, and for a profiled sheet, 1.5-2.0 m is acceptable.

However, even if the step required for the correct installation of the roof is exceeded, there is a way out. This is a reinforcing counter-lattice device. True, it will increase both the weight of the roof and the construction budget. Therefore, it is better to deal with the step of the rafters before the construction of the rafter system.

Craftsmen calculate the pitch of the rafters according to design features buildings, tritely dividing the length of the slope into equal distances. For insulated roofs, the step between the rafters is selected based on the width of the thermal insulation boards.

On our website you can find, which may also help you a lot during construction.

Rafter structures of layered type

Rafter structures of the layered type are much simpler in execution than their hanging counterparts. A justified plus of the layered scheme is to provide full ventilation, which is directly related to the longevity of the service.

Distinctive design features:

  • Mandatory presence of support under the skating heel rafter leg. The role of a support can be played by a run - wooden beam, based on racks or on the inner wall of the building, or the upper end of an adjacent rafter.
  • The use of Mauerlat for the construction of a truss structure on walls made of brick or artificial stone.
  • The use of additional runs and racks where the rafter legs, due to the large size of the roof, require additional support points.

The minus of the scheme is the presence of structural elements that affect the layout of the internal space of the operated attic.

If the attic is cold and the organization of useful premises is not supposed to be in it, then the layered construction of the truss system for the installation of a gable roof should be preferred.

A typical sequence of work on the construction of a layered truss structure:

  • First of all, we measure the height of the building, the diagonals and the horizontalness of the upper cut of the skeleton. When detecting vertical deviations of brick and concrete walls, we eliminate them with a cement-sand screed. Exceeding the heights of the log house we squeeze. By placing chips under the Mauerlat, vertical flaws can be dealt with if their magnitude is insignificant.
  • The floor surface for laying the bed must also be leveled. He, the Mauerlat and the run must be clearly horizontal, but the location of the listed elements in the same plane is not necessary.
  • We process everything wooden details structures before installation with flame retardants and antiseptics.
  • on concrete and brick walls we lay waterproofing for the installation of a Mauerlat.
  • We lay the Mauerlat beam on the walls, measure its diagonals. If necessary, we slightly move the bars and turn the corners, trying to achieve the perfect geometry. Align the frame horizontally if necessary.
  • We mount the Mauerlat frame. The splicing of the beams into a single frame is carried out by means of oblique cuts, the joints are duplicated with bolts.
  • We fix the position of the Mauerlat. Fasteners are made either with brackets to wooden plugs laid in the wall ahead of time, or with anchor bolts.
  • We mark the position of the bed. Its axis should recede from the Mauerlat bars at equal distances on each side. If the run will be based only on racks without lying down, the marking procedure is carried out only for these columns.
  • We install the bed on a two-layer waterproofing. We fasten it to the base with anchor bolts, with inner wall connect with wire twists or staples.
  • We mark the installation points of the rafter legs.
  • We cut out racks according to uniform sizes, because our bed is set to the horizon. The height of the racks must take into account the dimensions of the section of the run and the bed.
  • Installing racks. If provided by the project, we fix them with spacers.
  • We lay the run on the racks. We check the geometry again, then install the brackets, metal plates, wooden mounting plates.
  • We install a trial rafter board, mark the places of trimming on it. If the Mauerlat is set strictly to the horizon, there is no need to adjust the roof rafters in fact. The first board can be used as a template for making the rest.
  • We mark the installation points of the rafters. Folk craftsmen for marking usually prepare a pair of slats, the length of which is equal to the gap between the rafters.
  • According to the markup, we install the rafter legs and fasten them first at the bottom to the Mauerlat, then at the top to the run to each other. Every second rafter is screwed to the Mauerlat with a wire bundle. IN wooden houses the rafters are screwed to the second crown from the top row.

If the rafter system is done flawlessly, the layered boards are mounted in random order.

If there is no confidence in the ideal structure, then the extreme pairs of rafters are installed first. A control twine or fishing line is stretched between them, according to which the position of the newly installed rafters is adjusted.


The installation of the truss structure is completed by installing the filly, if the length of the rafter legs does not allow the formation of an overhang of the required length. By the way, for wooden buildings the overhang should “go beyond” the contour of the building by 50 cm. If the organization of the visor is planned, separate mini-rafters are installed under it.

Another useful video about the construction of a gable truss base with your own hands:

Hanging truss systems

The hanging type of truss systems is a triangle. The two upper sides of the triangle are folded by a pair of rafters, and the puff connecting the lower heels serves as the base.

The use of tightening allows you to neutralize the effect of the thrust, therefore, only the weight of the crate, the roof, plus, depending on the season, the weight of precipitation, acts on walls with hanging truss structures.

The specifics of hanging truss systems

Characteristic features of hanging type truss structures:

  • Mandatory presence of a puff, made most often of wood, less often of metal.
  • The ability to refuse the use of Mauerlat. A frame made of timber will be successfully replaced by a board laid on a two-layer waterproofing.
  • Installation on the walls of ready-made closed triangles - roof trusses.

The advantages of the hanging scheme include the space under the roof free from racks, which allows you to organize an attic without pillars and partitions. There are disadvantages.

The first of these is the limitation on the steepness of the slopes: their slope angle can be at least 1/6 of the span of a triangular truss, steeper roofs are strongly recommended. The second disadvantage is the need for thorough calculations for the competent device of cornice nodes.

Among other things, the angle of the truss truss will have to be set with jewelry accuracy, because. the axes of the connected components of the hanging truss system must intersect at a point, the projection of which must fall on the central axis of the Mauerlat or the lining board replacing it.

Subtleties of long-span hanging systems

Puff - the longest element of the hanging rafter structure. Over time, it, as is typical of all lumber, deforms and sags under the influence of its own weight.

Owners of houses with spans of 3-5m are not too concerned about this circumstance, but owners of buildings with spans of 6 meters or more should think about installing additional parts that exclude geometric changes in tightening.

To prevent sagging in the installation scheme of the truss system for a large-span gable roof, there is a very significant component. This is a pendant called a grandmother.

Most often, it is a bar attached with wooden surfs to the top of the truss truss. You should not confuse the headstock with the racks, because. its lower part should not come into contact with the puff at all. And the installation of racks as supports in hanging systems is not used.

The bottom line is that the headstock, as it were, hangs on a ridge knot, and a tightening is already attached to it with the help of bolts or nailed wooden plates. Threaded or collet type clamps are used to correct slack.

Adjustment of the tightening position can be arranged in the zone of the ridge knot, and the headstock can be rigidly connected to it with a notch. Instead of a bar in non-residential attics, reinforcement can be used to manufacture the described tightening element. It is also recommended to arrange a headstock or suspension where the puff is assembled from two bars to support the connection area.

In an improved hanging system of this type, the headstock is complemented by strut beams. The stress forces in the resulting rhombus are extinguished spontaneously due to the competent arrangement of the vector loads acting on the system.

As a result, the truss system pleases with stability with a slight and not too expensive upgrade.


Hanging type for attics

In order to increase the usable space, the tightening of the rafter triangles for the attic is moved closer to the ridge. A perfectly reasonable move has additional advantages: it allows you to use puffs as the basis for filing the ceiling.

It is attached to the rafters by cutting with a semi-frying pan with a duplication of a bolt. It is protected from sagging by installing a short headstock.

A noticeable drawback of the attic hanging structure is the need for accurate calculations. It is too difficult to calculate it on your own, it is better to use a ready-made project.

Which design is more cost effective?

Cost is an important argument for an independent builder. Naturally, the price of construction for both types of truss systems cannot be the same, because:

  • In the construction of a layered structure for the manufacture of rafter legs, a board or beam of small section is used. Because layered rafters have two reliable supports under them, the requirements for their power are lower than in the hanging version.
  • In the construction of a hanging structure, the rafters are made of thick timber. For the manufacture of puffs, a material similar in cross section is required. Even taking into account the rejection of the Mauerlat, the consumption will be significantly higher.

Saving on the grade of material will not work. For the bearing elements of both systems: rafters, purlins, beds, Mauerlat, attendants, racks, lumber of the 2nd grade is needed.

For crossbars and puffs working in tension, you will need the 1st grade. In the manufacture of less responsible wooden slips, the 3rd grade can be used. Without counting, we can say that in the construction of hanging systems, expensive material is used to a greater extent.

Hanging trusses are assembled in an open area next to the object, then transported assembled upstairs. To lift weighty triangular arches from a bar, you will need equipment, for which you will have to pay rent. And the project for complex nodes of the hanging version is also worth something.

Video instruction on the installation of a truss structure of a hanging category:

There are actually many more methods for constructing truss systems for roofs with two slopes.

We have described only the basic varieties that are actually applicable for small country houses and buildings without architectural designs. However, the information provided is sufficient to cope with the construction of a simple truss structure.

The truss system is the basis of the roof, the reliability and strength of the roof, its ability to withstand precipitation and wind depends on it. The design of the truss system is determined by the shape of the roof and the features of the layout of the house, as well as the materials used. A do-it-yourself truss system is usually made of wood, but other materials, such as a metal profile, can also be used.

Types of rafters and their application

The choice of a truss system is a crucial step that requires knowledge of the design of each type of roof. Rafters can be:

  1. Laminated rafters based on a ridge run and Mauerlat. They are used in the construction of a single-pitched, simple gable roof, as well as one of the elements of a hip and broken roof. mansard roof.
  2. Sliding rafters - a type of layered rafters used for wooden buildings that give a lot of shrinkage. Their difference is the sliding fastening of the rafters to the Mauerlat, which allows you to compensate for the shrinkage of the walls without deformation of the roof.
  3. Hanging rafters - a system of rafters tied with crossbars or puffs, usually used in the construction of a simple gable roof, as well as the upper rafters of a mansard roof. In the hanging rafter system, there is no ridge run, and in the upper part the symmetrical rafter legs rest directly on each other.
  4. Sloping rafters, otherwise called angular or diagonal. They are used to make a three-pitched or four-pitched roof, as well as for roofs with complex geometry.

Elements of the truss system

Any rafters are designed to distribute and transfer the load of the roof to the walls of the house. The main elements on which the rafters rely are:

  • Mauerlat - a beam fixed on the upper plane of the walls around the perimeter of the whole house;
  • Beds - support bars laid on internal load-bearing partitions or columns;
  • Beams of the ceiling of the upper floor;
  • Racks and supports;
  • Runs - horizontal support elements laid along the roof axis on racks.

The truss truss consists of the following elements:

  • Rafter legs - boards or beams that form the contour of the roof and are laid with a certain step;
  • Puffs or crossbars - horizontal elements that pull paired rafter legs together;
  • Struts - supports set at an angle and supporting the rafter legs;
  • Filly - boards fixed at the lower end of the rafters and forming roof overhangs;

Narozhniki - short rafters resting on diagonal rafters in a hip roof.

All these elements in private construction are usually made of wood - timber or coniferous boards, naturally dried. The tree is impregnated with an antiseptic, which allows you to extend its service life. The thickness and section of the elements is determined by calculation.

Laminated rafter technology

  1. Before construction begins, it is necessary to sketch the roof and calculate its dimensions. The cross section and pitch of the rafters, as well as the need to install additional supports and struts, are also determined by calculation.
  2. Support elements are laid and exposed: mauerlat, beds and floor beams, racks, ridge and intermediate runs. These operations are described in detail in the articles on different types roofs:
  3. Make a rafter template. To do this, take a board with a width corresponding to the estimated length of the rafters, with the same width, but with a smaller thickness - it is lighter and easier to fit exactly in place. The board is applied to the installation site of the extreme rafter with one end to the ridge run, the other to the Mauerlat.
  4. At the top of the template mark the top gash. The shape of the cut should be such that the board lies on the ridge run and at the same time fits snugly against the opposite rafter. The depth of the cut should be no more than 1/3 of the width of the board.
  5. After sawing out the upper cut, the template is once again applied in place and the lower cut is marked out - it should rest on the Mauerlat, without leaving large gaps. The end of the template is filed at an angle so that the cut is in a vertical plane.

  6. The resulting template is applied at the installation site of all rafter legs, checking whether it will be necessary to fit in place. If the template fits perfectly (which rarely happens), you can immediately make the required number of rafter legs. If adjustment of the lower notch is needed, then only the upper part of each rafter is cut out according to the templates, and the lower notch is done in place each time.
  7. The rafters are placed with the established step calculation. Usually it is from 50 to 120 cm and depends on the type of roofing, namely on its severity, and on the expected snow load. The heaviest coatings are slate and ceramic tiles, but they are rarely used today. More often, the choice is made in favor of more modern, light and reliable materials: metal tiles, ondulin, soft roof. For them, the pitch of the rafters can be chosen about 100 cm without performing complex calculations.
  8. First, rafters are installed from the side of the gables. The rafter leg is supported on the ridge run and the Mauerlat and fixed on two nails 100-150 mm in each attachment point. Having installed the rafter pair, they additionally fasten it: in the upper part with the help of metal plates and self-tapping screws on one side and corners with a stiffener on the other, in the lower part - with brackets or also on the corners.

  9. After installing the rafters from both gables of the roof, a twine is pulled between them and the rest of the rafters are aligned along it. Rafters are fastened in the same way.

  10. Install struts, if required by the results of the calculation. The struts are made from the same material as the rafters. A board of suitable length is applied at the desired angle to the rafter and the bottom cut is marked. It is important to consider what the brace will rely on: on the floor beam or on the bed, the shape of the lower gash depends on this. After completing the lower cut, the brace is put in place and the cut line along the rafters is marked. The prepared brace is placed at a distance between the beams and rafters and secured with metal plates or corners.

Roof strut installation


Technology for the implementation of hip diagonal rafters

  1. Since the rafters for the hip roof are installed diagonally, the usual methods of attaching them are not suitable. In addition, the load on diagonal rafters is much higher than on layered or hanging ones, so the material for their implementation must have a larger cross section. You can use a beam with a thickness of 100 mm or more, but practice shows that it is more convenient to make these rafters from two folded and fastened boards of standard thickness.
  2. The diagonal rafters are supported by the upper end on the racks, the lower end - on the Mauerlat bars converging at right angles. They are marked in place, and their main feature is that the cuts are not made perpendicular to the plane of the board, but at an angle of 45 degrees. When making rafters from spliced ​​boards, first one side is performed with oblique cuts, then the second, in a mirror image.
  3. The boards are pulled together with screws, nails or studs. Fasten hip rafters using pads and screws.

A video will help you better understand the basic techniques for building a truss system with your own hands.

When doing any truss system with your own hands, it is important to carefully secure all knots and connections and remember that the roof is the main protection of your house from bad weather. Therefore, it is important not only to make a high-quality frame, but also to choose the right one, for example, corrugated board, and lay it correctly.

A gable or gable roof is a practical design that is not difficult to install and install. Its main elements have strong protection against various negative phenomena. With a properly executed device and choosing the optimal angle of inclination of the slopes, the attic space can be used as a living room. In this article we will analyze the device of a gable roof.

The design of the gable roof truss system can be made using layered or hanging rafters. Let's analyze the characteristics of the truss system.

oblique

Laying method - for installation, two supports are required for the bottom and top of each rafter leg. This design is used in a wooden house, where there are powerful columns or internal load-bearing walls. This system has its own design features, without which their installation is impossible. Design features of the layered method:

  • Due to the large size of the ceiling, the design requires additional support points. To achieve strength, additional racks and runs are used;
  • When building brick walls, it is recommended to use Mauerlat;
  • Installing the support under ridge element rafter leg.

The disadvantage of the layered method is the impact on the layout of the entire internal space of the attic. If the attic is planned to be used for storing household items, the layered method is ideal for installing a gable roof.

hanging

Hanging method - for its installation, it is necessary to have a support for the lower rafter legs. They are used in the device at home, where it is not possible to fix the support under the ridge run. The main design features of the hanging method include:

  • Rafter trusses can be used to install ready-made triangles on walls;
  • Mauerlat can be replaced with a board, which is laid on a two-layer waterproofing;
  • The puff is made of wood.

The disadvantage of such a system is that for its construction it is necessary to perform the correct calculation, which will allow you to correctly perform the eaves nodes.

For information! The combined method of installing a gable roof includes the use of layered and hanging methods. This method of constructing the structure allows you to perform a uniform load and create slopes that will not go beyond the selected roof structure.

The photo shows a rafter system of a hanging and layered type.


The truss system consists of several important elements:

  • skating run;
  • crossbars;
  • spacers;
  • inclined struts;
  • rafter legs;
  • vertical racks.

As a material for the manufacture of rafters and other structural elements of a gable roof, iron, reinforced concrete and wood are used.

The main elements and device of the roof

The device of the gable roof truss system in a wooden house consists of two inclined slopes located at an angle and median between themselves in the ridge. The end side of the slopes resembles the shape of a triangle, which is called the pediment. The design of a gable roof includes the following building elements:

  • Mauerlat is a roof support beam wooden house, it is laid on the top of the building. The main task of this part is to evenly distribute the load from the roof to the walls. IN wooden house the role of the Mauerlat is performed by the upper crown of the log house.
  • rafter legs- necessary for the construction of a triangle of construction, they fix the roof on both sides and connect it in the area of ​​\u200b\u200bthe ridge. Such a complex is called a truss system. The rafters perform the main contour of the roof, the installation step of the legs depends on the size and shape of the roofing.

For information! You can increase the strength of the rafter legs by laying the board on the end of the structure.

  • Racks - are supports that support the truss system of wooden houses. They are mounted vertically in the place of the ridge.
  • Tightening - performs the task of fastening the legs, due to which the entire complex is firmly fixed and does not move apart.
  • Beds - also perform the function of supporting the entire structural system

The photo shows a gable roof and its main elements.

  • Runs - is an element that supports the roof structure.
  • Struts - are inclined supports that are set at a certain angle and connected to the farm. Such a roofing device allows you to build a rigid structure that can withstand absolutely any load.
  • Lathing - is an assembled system of boards, on top of which the roofing is laid.
  • Filly - this part is installed on the condition that the legs are not long enough, due to which it is impossible to make an overhang. The gable roof includes this element, with the help of which overhangs are formed.
  • Overhang - a structural element of the entire system, responsible for the rapid and unhindered removal of precipitation. Overhangs protect the walls and load-bearing parts of the house from destruction, cracking and cracks.

You can learn more about how a gable roof is arranged and why all the structural elements are needed from the video

The gable design has a simple system that can be done independently. When constructing the complex, experts recommend paying special attention to the Mauerlat. It is this element that is responsible for the strength of the structure and its long-term operation.

Roof installation is a complex multi-stage process. In order to independently assemble and install the truss system, it is necessary to carefully study the methods of connecting the elements, calculate the length of the rafters and the slope angle, and select the appropriate materials. If you do not have the necessary experience, you should not take on complex designs. The best option for a small residential building - do-it-yourself gable roof.

A standard roof of this type consists of the following elements:


Mauerlat is a beam laid on top of the walls along the perimeter of the building. It is fixed with threaded steel rods immured into the wall or anchor bolts. The beam must be made of coniferous wood and have a square section of 100x100 mm or 150x150 mm. Mauerlat takes on the load from the rafters and transfers it to the outer walls.

rafter legs- This long boards section 50x150 mm or 100x150 mm. They are attached to each other at an angle and give the roof a triangular shape. The design of their two rafter legs is called a truss. The number of farms depends on the length of the house and the type of roofing. Minimum distance between them is 60 cm, the maximum is 120 cm. When calculating the pitch of the rafter legs, one should take into account not only the weight of the coating, but also the wind load, as well as the amount of snow in the winter.

It is located at the highest point of the roof and most often represents a longitudinal beam connecting both slopes. From below, the timber is supported by vertical racks, and the ends of the rafters are attached to the sides. Sometimes the ridge consists of two boards, which are nailed to the top of the rafters on both sides and connected at a certain angle.

Racks - vertical bars with a section of 100x100 mm, located inside each farm and serving to transfer the load from the ridge run to the load-bearing walls inside the house.

The struts are made from timber scraps and set at an angle between the uprights and the rafters. The side faces of the truss are strengthened with struts, the bearing capacity of the structure is increased.

Puff - a beam connecting the lower parts of the rafters, the base of the truss triangle. Together with struts, such a beam serves to strengthen the truss, increases its resistance to loads.

Lying is a long beam with a section of 100x100 mm, laid along the central bearing wall on which the vertical posts rest. Lying is used when installing layered rafters, when the run between the outer walls is more than 10 m.

The crate is a board or timber stuffed on the rafters. The crate is solid and with gaps, depending on the type of roof. It is always attached perpendicular to the direction of the rafters, most often horizontally.

If there is no more than 10 m between the outer walls and there is no load-bearing wall in the middle, arrange hanging rafter system. With such a system, the upper ends of adjacent rafters are sawn at an angle and connected to each other with nails, excluding the installation of racks and ridge timber. The lower ends of the rafter legs rest on the outer walls. Due to the lack of racks, the attic space can be used to equip the attic. Very often, floor beams perform the function of puffs. To strengthen the structure, it is recommended to install the upper puff at a distance of 50 cm from the ridge.

In the presence of a central supporting wall, the arrangement is more justified layered truss system. A bed is laid on the wall, support posts are attached to it, and a ridge beam is nailed to the posts. This installation method is quite economical and easier to perform. If the ceilings in the interior are designed at different levels, the racks are replaced brick wall dividing the attic into two halves.

The installation process of the roof includes several stages: fastening the Mauerlat to the walls, assembling the truss trusses, installing the rafters on the floors, installing the ridge, fastening the batten. All wooden elements before assembly are carefully treated with any antiseptic composition and dried in the air.

For work you will need:

  • timber 100x10 mm and 150x150 mm;
  • boards 50x150 mm;
  • boards 30 mm thick for lathing;
  • ruberoid;
  • metal studs;
  • jigsaw and hacksaw;
  • hammer;
  • nails and screws;
  • square and building level.

in wooden houses Mauerlat functions are performed by logs of the last row, which greatly simplifies the workflow. To install the rafters, it is enough to cut on inside logs grooves of the appropriate size.

in brick houses or buildings from blocks, the installation of the Mauerlat is as follows:


Mauerlat bars should form a regular rectangle and be in the same horizontal plane. This will facilitate further installation of the roof and provide the structure with the necessary stability. In conclusion, markings are made on the bars for the rafters and grooves are cut along the thickness of the bar.

When choosing a hanging truss system, it is necessary to assemble the trusses on the ground, and then install them above the floors. First you need to draw up a drawing and calculate the length of the rafter legs and the angle of their connection. Typically, the roof slope is 35-40 degrees, but in open, heavily ventilated areas, it is reduced to 15-20 degrees. To find out at what angle to connect the rafters, you should multiply the angle of the roof by 2.

Knowing the length of the run between the outer walls and the angle of connection of the rafters, you can calculate the length of the rafter legs. Most often, it is 4-6 m, taking into account the cornice overhang 50-60 cm wide.

The upper ends of the rafters can be fastened in several ways: overlap, butt and "in the paw", that is, with cut grooves. For fixing use metal pads or bolts. Next, the lower and upper puffs are mounted, and then the finished trusses are lifted up and installed above the ceilings.

The extreme trusses are attached first: with the help of a plumb line, the rafters are set vertically, the length of the overhang is adjusted and attached to the Mauerlat with bolts or steel plates. So that during the installation process the farm does not move, it is strengthened with temporary jibs from a bar. After installing the extreme rafters, the rest are exposed, keeping the same distance between them. When all the trusses are fixed, they take a board with a section of 50x150 mm, the length of which is 20-30 cm longer than the length of the eaves, and nail it along the upper edge of the slope. Do the same on the other side of the roof.

The first option: on the rafter leg, at the place of contact with the Mauerlat, a rectangular groove is cut out 1/3 of the beam width. Stepping back from the top of the box 15 cm, a steel crutch is driven into the wall. The rafter is leveled, the grooves are aligned, then a wire clamp is thrown on top and the beam is pulled close to the wall. The ends of the wire are securely fixed on the crutch. The lower edges of the rafters are carefully cut with a circular saw, leaving an overhang of 50 cm.

The second option: the upper rows of walls are laid out with a stepped brick cornice, and the mauerlat is placed flush with the inner surface of the wall and a groove is cut in it for the rafter. The edge of the rafter leg is cut at the level of the upper corner of the eaves. This method is simpler than the others, but the overhang is too narrow.

Third option: ceiling beams are released over the edge outer wall by 40-50 cm, and truss trusses are installed on beams. The ends of the rafter legs are cut at an angle and rest against the beams, fixing with metal plates and bolts. This method allows you to slightly increase the width of the attic.

The device of layered rafters

1 shows the cutting of the struts of the rafters into a bed laid on intermediate supports, and in Fig. 2 - supporting the rafter leg on the Mauerlat

The procedure for installing a layered truss system:


When the main elements are fixed, the surface of the rafters is treated with flame retardants. Now you can start making the crate.

A beam of 50x50 mm is suitable for the crate, as well as boards with a thickness of 3-4 cm and a width of 12 cm or more. Waterproofing material is usually laid under the crate to protect the truss system from getting wet. The waterproofing film is laid in horizontal stripes from the eaves to the roof ridge. The material spreads with an overlap of 10-15 cm, after which the joints are fastened with adhesive tape. The bottom edges of the film must completely cover the ends of the rafters.

It is necessary to leave a ventilation gap between the boards and the film, so first wooden slats 3-4 cm thick are stuffed onto the film, placing them along the rafters.

The next stage is the sheathing of the truss system with boards; they are stuffed perpendicular to the rails, starting from the roof eaves. The step of the lathing is affected not only by the type of roofing, but also by the angle of inclination of the slopes: the larger the angle, the greater the distance between the boards.

After the installation of the battens is completed, they begin to sheath the gables and overhangs. You can close the gables with boards, plastic panels, clapboard, waterproof plywood or corrugated board - it all depends on financial capabilities and personal preferences. Sheathing is attached to the side of the rafters, nails or self-tapping screws are used as fasteners. Overhangs are also hemmed various materials from wood to siding.

Video - Do-it-yourself gable roof

Up