Strengthening the clip of the balcony slab estimate. What does the estimate for the repair of a balcony or loggia consist of? Sample estimate for draft material

In Soviet times, almost no one paid attention to the balcony. In other words, there it is, okay. For many, it then served as a smoking area or an area where you can place objects that are not subject to frost and precipitation.

But time passed, and the 90s came. And then more and more people began to pay attention to these extra square meters. Someone began to consider the balcony as an additional cellar, since they had to survive only at the expense of their crops. Someone wanted to make an additional warm room in the apartment from the balcony and use it, for example, for an office. And someone decided to combine the summer room with an adjacent room in order to increase the size of the latter.

All the desires described above are present in people today. And their implementation, as then, is impossible without converting the balcony into a loggia. And this already requires some financial costs. The only question is: "Which ones?"

In order to be able to figure out how much money will be needed to repair the loggia, below is an example of an estimate for this event.

Loggia parameters taken into account in the estimate:

  • Area - 5.1 sq.m.
  • Ceiling height - 2.8 m.
  • Glazing of the loggia - 1.7x4.2 m or 7.14 sq.m.
  • Glazing from the side of the room - 4.05 sq.m.

Plan

An example of an estimate for the repair of a loggia

Note: the estimate shows the average prices for Russia for 2015.


Estimated is one of important documents from which the repair, construction or reconstruction of any object begins. Drawing up an estimate for the repair of an apartment is a mandatory procedure, which is primarily necessary for the Customer. This fundamental document must be prepared as an annex to the contract.

ORDER APARTMENT REPAIR

The calculation of the estimate for the repair of apartments is carried out by a specialist - an estimator. To begin with, our specialist goes to the repair site, inspects the premises, makes measurements of the premises, gets acquainted with the condition of the floors, ceilings, walls, windows and doors, finds out the individual wishes of the Customer and receives the terms of reference.

Based on all the information received and the measurements made of the premises, project documentation and an estimate is made for overhaul apartments. You can do without an estimate, perhaps, only if you carry out a small redecorating or partial renovation of the interior. But still, an estimate is always needed, a description of the types of work tied to the estimate gives an undeniable number of advantages when working on construction site during the renovation. Thanks to the prepared preliminary estimate, the Customer receives detailed information on the list of types of work and materials necessary for the repair, and also sees the exact calculation of the cost of these finishing works and materials.

Typical commercial estimate does not look like an Excel spreadsheet, which must indicate the types of work, units of measurement and cost. Our company uses the services of experienced estimators, we also constantly monitor the prices of building materials, which allows us to significantly save money.

You, as a customer, have the ability to control the progress of work and cost items. When choosing a contractor for work, it is the analysis of the estimate that gives a complete picture of the cost of the work and allows you to evaluate the professionalism of the contractor.

We can immediately tell you that the prices for complex repairs are much lower than for individual types of work. Each order is individual! The cost of services depends on the types of work and their volume. Moreover, the larger the volume, the lower the price for repair and finishing work.

Sample estimate for finishing work

No./Pos

Name of works

unit.

Quantity

Price, rub

Amount, rub

Demolition works, garbage disposal

cleaning

Cleaning walls to concrete (from wallpaper, putty)

Ceiling cleaning to concrete (high-quality paint, putty

Cleaning the floor to concrete (from the old coating)

Other dismantling

Dismantling the plinth

Taking out the trash

Removal of construction debris

Electrical work

Wiring of electrical, telephone and television networks in walls and ceilings

Installation of sockets, switches, spotlights, machines

Wall plastering and floor leveling (screed)

Primer for concrete walls and ceilings

Leveling ceilings (improved plaster)

Wall leveling (improved plaster)

Painting works

Wall putty

Ceiling putty

wall pasting vinyl wallpaper

Ceiling painting water-based paint in 3 layers

Cleaning and painting pipes with heat-resistant paint

carpentry

Ceiling cornice laying, puttying and painting (styrofoam or polyurethane, width up to 3 cm)

Tiled work

masonry ceramic tiles on the floor

Cleaning

Multiple cleaning throughout the repair and after the repair

Total finishing work:

CUSTOMER

CONTRACTOR

__________

__________

Sample estimate for draft material

No./Pos

Name

unit.

Estimated price, rub

Estimated amount, rub

Materials for the main estimate

Mix plaster "Rotband"

Mix Betonokontakt, 5kg

Insulating tape

Mounting boxes

Junction boxes

Alabaster G-5 ( gray color) by 20kg

Copper wire in double insulation PUNP 3x1.5

Copper wire in double insulation PUNP 3x2.5

Putty "Vitonit-LR" (Fin.)

Ready-made finishing putty SHEETROCK 5.6kg (3.5l) ready putty

bucket 3.5l

Deep penetration primer, canister 10l

Latex-based water-based paint Fincolor Euro-7, white matte 9l

Glue for tiles Fliesenkleber KNAUF (Fliesen KNAUF), 25kg

Polyethylene roll 3 m wide

Dowels, screws, self-tapping screws, nails, bolts and other fasteners

Consumables and auxiliary materials, one-time tools

Total for building and finishing materials

Transportation, loading, overheads, contingencies, tool depreciation, budgeting, etc. from the cost of materials

Total with transport costs and other expenses

Dismantling, construction and finishing works, garbage removal

TOTAL Estimated Costs

59749

CUSTOMER

CONTRACTOR

__________

__________


For an approximate calculation of the cost of repairing premises, use our online calculator. On our online repair cost calculator, you can calculate the approximate cost of repair work with draft materials. You just need to choose the type of repair (redecoration, overhaul, renovation), select the name of the room in which you are going to make repairs, then enter the area of ​​\u200b\u200bthe room in square meters by gender, and the rest online calculator he calculates everything himself and gives out in the column Total Estimated estimated cost of your refurbishment.

Room renovation cost calculator - online

If you do not want to manually calculate the floor area or you did not understand something when describing the calculations, then you can use our calculator and calculate floor or ceiling area automatically.

For the calculation it is necessary measure in meters length, width of the room and enter the data in order by filling out the form and you will automatically receive a calculation floor or ceiling area in square meters.

Floor and ceiling area calculator

H We will not load you with tedious mathematical calculations. You only need to measure the basic parameters, and the wallpaper calculator will approximately calculate the required number of wallpapers for your room. Those who want more accurate calculations and measurements can read the article above. How to calculate how much wallpaper you need.

A sample of a ready estimate for repair and finishing work in an apartment with a total area of ​​​​64 m2, a new building at the address: Residential Complex "Mkr.Finsky-Potapovo 3A".

Estimate No. 4 for repair and finishing work

Estimate for the purchase of rough materials

Name of works Unit rev. Qty

Rate

in rubles

Price

in rubles

Dismantling works
1 Ceiling stitching (rust) l.m. 8 150 1200
2 Dismantling sockets, switches, lamps PC. 12 75 900
3 Dismantling the electrical panel assembly PC. 1 650 650
Total: 2 750
Construction works
1 Laying of partitions from tongue-and-groove blocks or foam concrete up to 100 mm thick sq.m 5,8 420 2436
2 Metal jumper device l.m. 2 280 560
3 Block bath screen device PC. 1 1100 1100
4 Steam-thermal insulation device ("penofol", "penoplex") balcony - floor, ceiling, walls sq.m 27 360 9720
5 Coating thermal insulation device "Akterm" sq.m 0 180 0
6 Waterproofing of joints adjacent to the street sq.m 6 185 1110
Total: 14 926
Painting and plastering works
1 Plastering of walls (by lighthouses) up to 20 mm sq.m 25 385 9625
2 Alignment of walls (as a rule) up to 10 mm - rooms, kitchen, corridor, pantry sq.m 154,5 200 30900
3 Alignment of ceilings (as a rule) up to 10 mm kitchen, hallway, pantry, balcony sq.m 28 250 7000
4 Seal of ceiling seams (rust) l.m. 8 150 1200
5 Surface primer (2 coats) ceiling, walls sq.m 0 60 0
6 Finishing grinding of surfaces - ceiling, walls sq.m 0 45 0
7 Putty ceilings for painting (complex of works) kitchen, hallway, pantry, balcony sq.m 28 350 9800
8 Painting ceilings with high-performance paint for 2 times sq.m 28 180 5040
9 Puttying walls for painting (a set of works) sq.m 154,5 280 44805
10 Wall painting with high-performance paint for 2 times sq.m 154,5 140 21630
11 Plastering window slopes up to 300 mm l.m. 15 260 3900
12 Puttying slopes for painting (a set of works) l.m. 15 280 4200
13 Painting slopes with high-quality paint for 2 times l.m. 15 180 2700
14 Installation of painting corners arched with sealing seams and joints l.m. 22 65 1430
15 Painting pipes up to 50 mm in diameter l.m. 26 120 3120
Total: 145 350
Joinery and carpentry
1 Installation door block(ready set) PC. 5 3000 15000
2 Installation of rack ceilings (up to 10 sq.m) sq.m 4,4 880 3872
3 Installation of plastic window sills up to 300 mm l.m. 4,5 750 3375
Total: 22 247
Tiled work
1 Wall cladding with tiles (size 250-250 mm) bath, toilet sq.m 25 850 21250
2 Hatch installation PC. 1 418 418
3 Tile hatch device (with installation of the mechanism) PC 1 1100 1100
4 Laying tiles on the floor (size 300-300 mm) bath, toilet, balcony sq.m 10 700 7000
5 Drilling holes in tiles PC. 12 160 1920
6 Grouting ceramic tiles (monocolor) sq.m 35 100 3500
7 Tiled thresholds l.m. 1 1000 1000
Total: 36 188
Floor arrangement
1 Floor waterproofing in bathrooms sq.m 4,4 185 814
2 Leveling screed device up to 3 mm sq.m 54,4 150 8160
3 Laminate installation (with underlay) sq.m 54,4 280 15232
4 Nut installation l.m. 3 150 450
5 Installation of skirting boards l.m. 65 130 8450
Total: 33 106
Ventilation work
1 Insert into the ventilation duct PC. 1 319 319
2 Installation of a ventilation duct (up to 2 m) PC 2 1650 3300
3 Fan installation (with connection) PC. 2 308 616
Total: 4 235
Heating
1 Alteration of the heating radiator connection unit PC. 3 4500 13500
2 Installing a heating radiator PC. 3 1500 4500
3 Removal / installation of the radiator for finishing work (without dismantling the bracket to the finished place) PC. 3 500 1500
Total: 19 500
Plumbing work
1 Temporary water supply device set 1 1650 1650
2 Plumbing fixture l.m. 6 600 3600
3 Seal of plumbing l.m. 6 120 720
4 Installation of fine filter with pressure regulator PC. 2 1400 2800
5 Collector installation (set of works) PC. 2 2000 4000
6 Pipe laying CHGV (m / layer, p / propylene, p / ethylene) l.m. 26 270 7020
7 Pad sewer pipes(PVC) l.m. 5 330 1650
8 Pipe insulation l.m. 26 50 1300
9 Installation storage water heater(boiler) PC. 1 3300 3300
10 Installation of the toilet bowl "Compact" PC. 1 2805 2805
11 Installation of "moidodyr" PC. 1 3000 3000
12 Mixer installation PC. 1 850 850
13 Installation of a hygienic shower PC. 1 850 850
14 Installing a heated towel rail PC. 1 3300 3300
15 Bath installation PC. 1 3700 3700
16 Mounting the tub mixer on the bar PC. 1 1250 1250
Total: 41 795
Electric installation work
1 Penetration device up to 30x30 mm l.m. 16 275 4400
2 Shtrab l.m. 16 35 560
3 Cabling l.m. 255 50 12750
4 Installing the socket box (with socket device) PC. 33 300 9900
5 Installation of a surface-mounted electrical distribution board PC. 2 650 1300
6 Installation of circuit breakers, differential automatic devices, RCDs PC. 12 250 3000
7 Installing a socket, switch PC. 30 130 3900
8 Installation of TV, Telephone, Internet sockets PC. 3 180 540
9 Installation of TV, Telephone, Internet splitter PC. 1 280 280
10 Installing a built-in (spot) lamp PC. 6 200 1200
11 Electric underfloor heating device sq.m 2 750 1500
12 Installation of underfloor heating relay PC. 1 350 350
13 Marking electrical installation sites (without a project) PC. 33 35 1155
Total: 40 835
Total for work: 360 932
Total for estimate No. 4: 360 932

Table No. 1 consumption of rough material.

Table No. 1 for the consumption of building and finishing rough material in an apartment with a total area of ​​​​64 m2, a new building at the address: LCD "Mkr. Finnish-Potapovo 3A".

Examples of samples of the table for accounting for the consumption of rough material

Name

material

pcs/m2

bags

price

general

price

1 Mix "Rodband" with a layer thickness of not more than 2 cm 87 370 32190
2 Sand concrete M300 with a screed layer thickness of not more than 5 cm 145 160 23200
3 Beacon plaster 0.6 45 40 1800
4 Plaster beacon 1.0 12 45 540
5 Betokontakt "EURO" 3 1350 4050
6 Primer "Prospectors" 5 450 2250
7 Foam block No. 5 in pieces 6 45 270
8 Foam block No. 7 in pieces 84 55 4620
9 Drywall moisture resistant 12 2 370 740
10 Gypsum putty "Fugenfuhler" 1 750 750
11 Mounting adhesive for blocks "Perlfix" 3 320 960
12 Glue tile "Flizen" 6 350 2100
13 Self-leveling floor "Prospectors" 8 320 2560
14 Putty "Vetonit" LR+ 9 750 6750
15 Gossamer "Oscar" 50m2 1 1150 1150
16 Profile 27/28 "Knauf" 6 100 600
17 Profile 60/27 "Knauf" 4 130 520
18 Finishing putty "Pro Form" 1 1350 1350
19 Pendant "Knauf" 40 20 800
20 Film -150 density 60 50 3000
21 Beam 50/50 planed 3 200 600
22 Board 150/20 planed 3 300 900
23 Trash bags 120 10 1200
24 Glue for gossamer "Oscar" 1 1350 1350
25 Coating waterproofing "Ceresit 65" 6 750 4500
26 Rule 2.5 1 500 500
27 Rule 2.0 1 400 400
28 Rule 1.5 1 300 300
29 Dowel nail 60/40 2 250 500
30 Grid facade 160 density 1 1250 1250
31 Putty "Uniflot-Knauf" 1 1100 1100
32 Bucket 12 liters 2 120 240
33 Bucket 20 liters 2 180 360
34 Basin 60 liters 1 350 350
35 Paper masking tape 5 70 350
36 Scotch packaging 2 70 140
37 Self-tapping screws 0.35 universal 2 130 260
38 Self-tapping screws 0.65 for wood 1 130 130
39 Self-tapping screws 0.75 for wood 1 130 130
40 Self-tapping screws 0.25 universal 2 130 260
41 Paint corner galvanized 18 35 630
42 Alabaster in bags 1 280 280
43 Silicone in a tube 1 140 140
44 Glue in tube "FixAll" 1 420 420
45 Crosses 1.5 for tile joints 4 100 400
46 Wedges for tile joints 2 100 200
47 Cable NUM 3/1.5 "Sevcable" 100 35 3500
48 Cable NUM 3/2.5 "Sevcable" 150 47 7050
49 Cable NUM 3/4 "Sevcable" 36 82 2952
50 Cable NUM 3/6 "Sevcable" 5 95 475
51 Corrugation 16 100 3 300
52 Corrugation 20 200 4 800
53 Internet cable "FTP" 10 22 220
54 TV cable "SAT 703" 40 25 1000
55 Telephone cable "KSPV" 10 12 120
56 Crab TV 1/3 1 250 250
57 Insulating tape 1 40 40
58 Perforated tape 1 180 180
59 Lamp 150v 5 40 200
60 Sockets for concrete 50 10 500
61 Automatic 10 amp. "ABB" 2 150 300
62 Automatic 16 amp. "ABB" 3 150 450
63 Automatic 25 amp. "ABB" 5 150 750
64 RCD "ABB" 1 1250 1250
65 DIF automatic 25 amp. 1 1350 1350
66 Armature 12 3 220 660
67
68 Material lifting "in tons" 8 1500 12000
69 Delivery of materials "gazelle" 4 1500 6000
70 Total: 147 787