Repair of power transformers. We repair power transformers Technological map of the power transformer

) on open switchgears, in the preparation of projects for the organization of construction (POS) and projects for the production of electrical work (PPER).

Current transformers of the TFZM and TFRM series (single-phase, electromagnetic, oil, outdoor installation, reference type) are designed to transmit information signals measuring instruments, protection and control devices in AC installations.

Current transformers (hereinafter referred to as "transformers”) TFZM 500 B and TFRM 750 A are made in the form of two stages (lower and upper), the rest are single-stage. Transformers 220 - 750 kV have a screen on the expander, and two-stage transformers, in addition, have an additional screen that closes the joint of the steps.

Routing contains instructions for organizinginstallations and installation technologies, a list of mechanisms, tools, information on the cost of materials, labor costing and work schedules.

It is assumed in the map that the work associated with the installation of transformers is carried out directly at the installation site, at the place of their installation.

All calculated indicators in the map are given for the installation of one group (three phases) of transformers.

Labor costs for adjustment work, installation schedules andcalculations are not taken into account.

The technological map was developed in accordance with the "Guidelines for the development of standard technological maps in construction." M., TsNIIOMTP Gosstroy of the USSR, 1987.

Forbids to open transformers and take oil samples.

Installation should be carried out with the participation of the chief engineer of the manufacturer.

Technical criteria and controls for operations and processes are given in Table. . Acceptance control of mounted transformers is carried out in accordance with SNiP 3.05.06-85. Upon acceptance of work, documentation is presented in accordance with the list of appendices. .

Current repairs of transformers are carried out in the following terms:

  • transformers of central distribution substations - according to local instructions, but at least once a year;
  • all others - as needed, but at least once every 3 years.

The first overhaul of substation transformers is carried out no later than 6 years after commissioning, and subsequent repairs are carried out as necessary, depending on the measurement results and the condition of the transformer.

The scope of the current repair includes the following works:

  • external inspection and repair of damages,
  • cleaning of insulators and tank,
  • descent of dirt from the expander,
  • adding oil and checking the oil gauge,
  • checking thermosyphon filters and, if necessary, replacing the sorbent,
  • checking the condition of the blow-out fuse, circulation pipes, welds, flange seals,
  • security check,
  • taking and checking oil samples,
  • carrying out preventive tests and measurements.

The scope of the overhaul includes all the works provided for by the current repair, as well as repair of the windings, magnetic circuit, checking the condition of the contact connections of the windings to the voltage switch and terminals, checking the switching devices, repairing their contacts and the switching mechanism, checking the condition of the transformer tank, expanders and pipelines, entry repair.

The transformer is taken out of operation for repairs under the following conditions:

  • strong internal crackling characteristic of an electrical discharge, or uneven noise,
  • abnormal and constantly increasing heating during normal load and cooling,
  • ejection of oil from the expander or destruction of the exhaust pipe diaphragm,
  • oil leaks and lowering its level below the permissible limit,
  • upon receipt of unsatisfactory results of the chemical analysis of the oil.

Aging of the winding insulation and moistening of the oil can lead to ground faults and phase-to-phase faults in the transformer windings, resulting in abnormal operating noise of the transformer.

A “steel fire” failure, which occurs due to a violation of the interlayer insulation of the core or the insulation of the tie bolts, leads to an increase in the heating of the case and oil under normal load, humming and characteristic crackling inside the transformer.

Increased “humming” in the transformer can occur due to the weakening of the magnetic circuit pressing, significant phase load asymmetry, and when the transformer is operating at increased voltage. A crackle inside the transformer indicates a flashover (but not a flashover) between the winding or case taps, or an open ground that could cause electrical discharges from the winding or case taps.

Typical transformer malfunctions when it is abnormally buzzing
Loosening the bolts securing the transformer cover and other parts (expander, exhaust pipe, etc.)Check and tighten all bolts
Transformer operates at high voltageSet the voltage switch to the appropriate position.
The pressing of the joints in the magnetic circuit is brokenThe tightening of the vertical studs tightening the rods with yokes has loosened. Repress the magnetic circuit, replacing the gaskets in the upper and lower joints of the magnetic circuit
The weakening of the pressing of the laminated magnetic circuitCheck all pressure bolts and studs and tighten loose ones.
Vibration of the outer sheets of the magnetic circuitWedged the sheets of the magnetic circuit
Transformer overloadReduce load
Reduce load unbalance
Short circuits between phases, between turns of windingsRepair or replace winding

Breaks in the windings are a consequence of the poor quality of the contact connections in the windings.

An open in the primary winding of a transformer connected in delta-star, delta-delta and star-star circuits leads to a change in the secondary voltage.

To determine the scope of the forthcoming repair, a transformer fault detection is carried out, which is a set of works to identify the nature and degree of damage to its parts. Based on fault detection, the causes, extent of damage and the necessary amount of repair of the transformer are determined. At the same time, the needs for materials, tools, fixtures for the repair are determined.

Typical malfunctions of power transformers
SymptomsPossible causes of malfunctionTroubleshooting
Overheating of transformersTransformer overloadedSet overload on instruments or by removing the daily current graph. Eliminate overload by switching on another transformer or disconnect less critical consumers
High air temperature in the transformer roomIf the air temperature is exceeded by 8 - 10 ° C at a distance of 1.5 - 2 m from the transformer in the middle of its height - improve the ventilation of the room
Reduced oil level in the transformerAdd oil to normal level
Damage inside the transformer (turn circuit, short-circuited circuits due to damage to the insulation of the tie bolts and studs, etc.)With the rapid development of these damages, an increase in oil temperature will occur, the release of gases and the operation of the gas protection on a signal or shutdown
Eliminate overload or reduce load unbalance in phases
Breakdown of windings on the case, between HV and LV windings or between phasesDeterioration of oil quality or lowering of its levelInsulation is tested with a megohmmeter or increased voltage
Deterioration of insulation quality due to its agingIf necessary, the winding is repaired, and the oil is topped up or completely changed.
Crackling inside the transformerOverlapping between windings or taps on the housingOpen the transformer and repair the taps of the windings and grounding
Ground break
Break in the windingsBadly soldered windingsOften a break occurs at the bend of the wire ring under the bolt
Damage in taps from windings to terminalsReplaced with a flexible connection in the form of a damper
The contact surfaces of the switching device are melted or burnt outThe switch is poorly assembled or there are short circuitsRepair or replace switch
Oil leakage from taps, flanges, welded jointsThe valve plug is badly ground, the gaskets of the flange connections are damaged, the tightness of the welded seam of the transformer tank is brokenGrind the valve, replace the gaskets or tighten the bolts on the flanges, weld the seams with acetylene welding. After welding, test the tank with water for 1 - 2 hours with a water column pressure of 1.5 m above the oil level in the expander

Disassembly of transformers

The disassembly of the transformer during the overhaul is carried out in the following order. Oil is drained from the expander, the gas relay, safety pipe and expander are removed; put plugs on the holes in the tank lid. With the help of lifting mechanisms, slings lift the cover with the active part of the transformer by lifting rings. Raising it by 10 - 15 cm, inspect the condition and position of the sealing gasket, separate it from the tank frame with a knife and, if possible, save it for reuse. After that, the active part is removed from the tank in sections convenient for removing oil sludge, washing the windings and the core with a jet of heated oil and fault detection. Then the active part is installed on a pre-prepared platform with a pallet. Having raised the active part of the transformer 20 cm above the level of the tank, they move the tank to the side, and the active part is installed on a solid platform for ease of inspection and repair. The windings are cleaned of dirt and washed with a stream of transformer oil heated to 35 - 40 ° C.

If the transformer inputs are located on the walls of the tank, then first remove the cover, drain the oil from the tank 10 cm below the input insulators and, having disconnected the inputs, remove the insulators, and then remove the active part from the tank.

Dismantling, inspection and repair of the transformer is carried out in a dry, closed and adapted room for the production of these works.

After removing the active part, the state of the magnetic circuit is checked - the density of the assembly and the quality of the lamination, the strength of the fastenings of the yoke beams, the condition of the insulating sleeves, washers and gaskets, the degree of tightening of nuts, studs, tie bolts, the state of grounding. Pay special attention to the condition of the windings - the wedging on the rods of the magnetic circuit and the strength of the fit of the windings, the absence of traces of damage, the condition of the insulating parts, the strength of the connections of the leads, dampers.

During the overhaul of the transformer, in addition to the above works, if necessary, the yoke of the magnetic circuit is unloaded with the iron being pressed out and the winding coils are removed.

Repair of the transformer magnetic circuit

The most common type of magnetic circuit of power transformers is flat (rod) (Fig. 123, a). The cross section of the yoke 6 and 7 is performed rectangular shape, and the rod - in the form of a multi-stage figure 3, close to a circle. The magnetic circuit is pulled together by yoke beams 5 n 8 using through studs 4 and tie rods 2.

Rice. 123. Flat (a) and spatial (b) magnetic cores of the transformer:
1 - axes of the rods; 2 - vertical tie rods: 3 - multi-stage rod figure; 4 - through studs; 5, 8 - yoke beams; 6, 7 - cross sections yoke; 9 - support beam; 10 - bandage; 11 - insulating tube; 12 - insulating gasket; 13 - Belleville spring, 14 - insulating gasket.

Transformers with a power of 250 - 630 kVA are produced with pinless magnetic cores. The pressing of the rod plates in these transformers is carried out by means of strips and wedges driven between the magnetic circuit and the cylinder. Recently, the industry has been manufacturing 160 - 630 kVA power transformers with a spatial magnetic circuit (Fig. 123, b). The magnetic core of such a transformer is a rigid structure, the vertical axes of the rods 1 of which have a spatial arrangement. The steel sheets of the rod are pressed with a bandage 10 of insulating material or a steel tape with a lining of insulating material instead of studs. The upper and lower yokes are pulled together by vertical tie rods 2 by means of nuts, under which belleville springs 13 are placed. Insulating gaskets 14 are used to isolate the studs from the yoke, and insulating tubes 11 are used from the rods. The entire structure of the magnetic circuit is fastened with studs to the support beams 9.

The spatial magnetic circuit is made butt instead of laminated, since the yoke and rods are connected into a magnetic circuit by docking. To avoid shorting between the steel of the yoke and the rod, an insulating gasket 12 is laid between them.

In previously produced transformers, the magnetic cores were pulled together by horizontal studs, insulated from the steel of the magnetic core and passing through holes in the plates.

The disassembly of the magnetic circuit is as follows: unscrew the top nuts of the vertical studs and the nuts of the horizontal studs, remove them from the holes in the yoke, remove the yoke beams and proceed to unload the upper yoke of the magnetic circuit, starting with the outermost packages of two or three plates. The plates are folded in the same sequence in which they are removed from the yoke and tied into packages.

In magnetic cores tied with horizontal studs, the insulation of the studs is often damaged, which leads to short circuits of steel plates and causes strong heating of iron by eddy currents. During the repair of a magnetic circuit of this design, the insulating sleeve is replaced with a new one. In the absence of spares, the sleeve is made from bakelite paper, wound on a hairpin, impregnated with bakelite varnish and baked. Insulating tubes for studs with a diameter of 12 - 25, 25 - 50 and 50 - 70 mm are made with a wall thickness of 2 - 3, 3 - 4 and 5 - 6 mm, respectively. Pressure insulating washers and spacers for studs are made of electrical cardboard with a thickness of 2 mm or more.

Restoration of the broken insulation of the magnetic circuit plates begins with boiling the sheets in a 10% sodium hydroxide solution or in a 20% trisodium phosphate solution, followed by washing the sheets in hot (50 - 60 ° C) running water. After that, a mixture of 90% hot-drying varnish No. 202 and 10% pure filtered kerosene is carefully sprayed onto a steel sheet heated to 120 ° C. Glyptal varnish No. 1154 and benzene and gasoline solvents can be used to isolate the plates. After applying the insulation layer, the plates are dried at 25 C for 7 hours. For large volumes of work, special machines are used for varnishing the plates, and special ovens are used for baking and drying them.

When replacing worn-out plates, new steel plates made according to samples or templates are used. In this case, the sheets are cut in such a way that the busbar side of the plates is along the rolling direction of the steel. Holes for tie rods in the plates are made by stamping, not drilling. After making the plate, I cover it! isolated in one of the above ways.

Laying starts from the central package of the middle rod, laying the plates with the insulated side inside the yoke. Then, the extreme packages are blended, starting with long plates and avoiding overlapping of narrow plates of rods and gaps in the joints. The holes in the yoke plates must exactly match the holes in the rod plates. The plates are leveled by hammer blows on a copper or aluminum bus. A well-stitched yoke has no gaps between the layers of plates, gaps, or damage to the insulation between the plates at the junction.

After leveling the upper yoke, the installation of the upper yoke beams is performed and pressing with their help of the magnetic circuit and windings. The yoke beams in transformers are isolated from the plates with an annular washer made of electric cardboard 2-3 mm thick with pads attached on both sides.

On both sides of the upper yoke, yoke beams are installed into the openings of the beams, four vertical tie rods with insulating tubes are inserted, cardboard and steel washers are put on the ends of the studs and tightened with nuts, Grounding of the vertical yoke beams is carried out with several tinned copper tapes.

Nuts are tightened on the tie rods, pressing the upper yoke, and the nuts of the vertical pressing rods are evenly tightened; the winding is pressed, and then the upper yoke is finally pressed. They measure the insulation resistance on the studs with a megger, unscrew the nuts on the studs so that they do not unscrew themselves during the operation of the transformer.

Repair of transformer windings

Windings of power transformers are the main element of the active part. In practice, windings are damaged much more often than other elements of the transformer.

Depending on the power and rated voltage in transformers, various designs windings. So, in power transformers with a power of up to 630 kVA at low voltage, mainly single- and double-layer cylindrical windings are used; with a power of up to 630 kV -A at the highest voltage of 6, 10 and 35 kV, multilayer cylindrical windings are used; with a power of 1000 kVA and more, screw windings are used as LV windings. At the helical winding, the rows of wound turns are arranged so that oil channels are formed between them. This improves winding cooling conditions due to cooling oil flows. Helical winding wires are wound on paper-bakelite cylinders or split templates using electrical cardboard strips and spacers, which form vertical channels along the inner surface of the winding, as well as between its turns. Screw windings have high mechanical strength. Repair of windings of power transformers can be carried out without unloading or with unloading of magnetic cores.

Slight deformation of individual turns, damage to small sections of wire insulation, loosening of windings, etc., are eliminated without dismantling the active part of the transformer.

When repairing the windings without removing them, the deformed turns of the windings are straightened by hammer blows on a wooden gasket superimposed on the turn. When repairing turn insulation without dismantling the windings, oil-resistant varnished cloth (LKhSM brand) is used, which is applied to the bare conductor of the turn. The conductor is pre-wrung out with a wooden wedge for the convenience of working on the insulation of the coil. Lacquered cloth tape is wound overlapping with overlapping of the previous turn of the tape on V2 part of its width. A general bandage of cotton tape is applied to the coil isolated with varnished cloth.

Pre-pressing of weakened windings, the design of which does not provide for pressing rings, is carried out using additional insulating gaskets made of electrical cardboard or getinaks. To do this, a wooden wedge is temporarily hammered into adjacent rows of winding to weaken the density of the gaskets, thus ensuring the entry of the driven pressing gasket in a weakened place. Clog the pressure pad and move on to the next place. This work is carried out along the entire circumference of the winding, clogging the spacers between the yoke and additional insulation.

Significant damage to the windings (turn short circuits, breakdown of the insulation of the windings on the steel of the magnetic circuit or between the HV and LV windings, etc.) is eliminated after the windings are removed.

To dismantle the windings, the magnetic circuit of the transformer is unloaded. Work begins with unscrewing the upper nuts of the vertical studs. Then the nuts of the horizontal studs are unscrewed, the horizontal pressing studs are removed from the hole in the yoke and the yoke beams are removed. One of the yoke beams is pre-marked symbol(HV or NN).

The unloading of the plates of the upper yoke of the magnetic circuit begins simultaneously from the side of the HV and LV, taking out 2 - 3 plates alternately from the extreme packages. The plates are laid in the same order in which they were removed from the yoke. and tied into packages. To protect the plates of the magnetic core rods from damage to the insulation and scattering, they are tied by threading a piece of wire into the hole for the pin.

The dismantling of the windings of transformers of small power is carried out manually, and with a power of 630 kV A and above - using removable devices. Before lifting, the winding is firmly tied with a rope along the entire length and the grips of the device are carefully brought under the winding.

Damaged coils are replaced with new ones. If a new coil during storage could be moistened, then it is dried in a drying chamber or with infrared rays.

The copper wire of the failed coil is reused. To do this, the insulation of the wire is burned in the furnace, it is washed in water to remove residual insulation, straightened and wound with new insulation. For insulation, cable or telephone paper 15–25 mm wide is used, wound onto the wire in two or three layers. bottom layer impose end-to-end, and the top overlap with overlapping of the previous turn of the tape by ½ or ¼ of its width. Strips of insulating tape are glued together with bakelite varnish.

Often, a new coil is made to replace a failed coil. The method of manufacturing windings depends on their type and design. The most perfect design is a continuous winding, produced without breaks. In the manufacture of a continuous winding, the wires are wound on a template wrapped with a sheet of electrical cardboard 0.5 mm thick. Laths with spacers are laid on the cylinder installed on the winding machine to form channels and the end of the winding wire is fixed with cotton tape. Winding of turns of continuous winding can be done clockwise (right-hand version) and counter-clockwise (left-hand version). Turn on the machine and guide the winding wire evenly along the cylinder. The transitions from one coil to another during winding are determined by the settlement note and are performed in the interval between the same two rails. The places of wire transitions are additionally insulated with boxes of electrical cardboard, fixed with a cotton tape. After winding is completed, bends are made (external and internal), arranging them in accordance with the drawings, and isolating them. At the ends of the coil, insulating support rings are installed and removed from the machine. The coil is pulled together with metal plates by means of tie rods and sent for drying in a drying chamber.

The scheme of the algorithm and the technological map for the manufacture of a multilayer winding of a HV transformer with a power of 160 kV A and a voltage of 10/04 kV are given below.

Technological map of winding manufacturing
No. p / pWinding manufacturing procedureTool, material
1. Prepare a bakelite cylinder, for which check its condition and dimensions, strengthen it on the machine. If there is no ready-made one, make a cylinder of electric cardboard longer than the length of the winding by 32 mmYardstick
Electrocardboard EMC 1.5 - 2 mm thick
2. Prepare insulating material for interlayer insulation.
For the manufacture of layered insulation, electric cardboard is used with a thickness equal to the diameter of the wire (or the thickness of the coil); the finished insulation is wrapped with telephone paper.
Scissors, cable paper (0.1 m), EMC electric cardboard (0.5 mm) telephone paper (0.05 mm)
3. Install the spool of wire on the turntable, adjust the wire tension.Turntable, PB winding wire with a diameter of 1.45 / 1.75.
4. Install the end equalizing belt on the cylinder close to the cheek of the template. Bend the wire lead at a right angle.Ribbons (keeper, lacquer).
Isolate the output and fix.
Pass the tap through the cutout in the template and fix the template on the faceplate of the winding machine.Hammer, fiber wedge.
Wind one layer of the coil, sealing its turns in the axial direction with a wedge.Cable paper 0.1 mm.
Wrap the first winding layer with layers of cable paper.
5. Wind the winding layers alternately. Each transition from layer to layer should lag behind by one third of the circle. At the end of each layer (2 - 3 turns before the end), an equalizing belt is installed (as in 4). Between the layers, beech planks are installed in accordance with the settlement note.Manual scissors for metal.
Beech planks with cardboard boxes.
When making taps on beech strips, according to the settlement note, the exit points of the taps are marked.
6. Make withdrawals in accordance with the settlement note. The cross section of the taps must be at least 1.5 - 2 sections of the winding wire with a diameter of up to 1 mm and 1.2-1.25 - with a diameter of more than 1 mm.
Insulate the end of the coil with tape in a semi-overlapping layer.
Pass the end of the coil through the ribbon loop and tighten it. Cut off the end of the tape.
Lay the cable paper half-overlapping on the upper layer windings.
Strip the insulation at the ends of the winding.
7. Remove the winding from the machine.Hammer.
Tie the winding in the axial direction in 3 - 4 places with tape.
Fasten in connected places with electric cardboard pads.
8. Soak the winding in varnish for at least 15 minutes and allow the varnish to drain (15 - 20 minutes).Installation for impregnation and drying.
Glyftel varnish GF-95. 1
Dry the winding at 100°C for 5-6 hours.
Bake the varnish of the winding at a temperature of 85 - 90 ° C for 18 - 20 hours with hot air blowing.
Remove from the oven and cool the winding.

The winding is dried at a temperature of about 100 ° C for 15 - 20 hours, depending on the volume of the coil, the degree of insulation moisture, the drying temperature, etc. Then it is pressed, impregnated at a temperature of 60 - 80 ° C with TF-95 varnish and baked at a temperature of 100 ° C for 10-12 hours. The winding is baked in two stages - first, the impregnated winding is dried at a slightly lower temperature to remove solvents remaining in the insulation, and then the temperature is increased to bake the winding. Drying and baking the winding increase the dielectric strength of the insulation and the mechanical strength of the coil, giving it the necessary solidity.


Rice. 124. Machine for winding transformer windings:
1 - electric motor; 2 - body; 3 - belt drive; 4 - counter of turns; 5 - clutch; 6 - spindle; 7 - textolite disc; 8 - nut; 9 - template; 10 - control pedal.

For the manufacture of windings, various machines are used. The console winding machine for winding transformer windings of small and medium power (up to 630 kVA) (Fig. 124) consists of a template with two wooden counter wedges 9, clamped textolite disks 7 and fixed nuts 8. The template is mounted on a spindle 6, which rotates from an electric motor 1 through a belt drive 3. To count the number of turns of wire, the machine has a coil counter 4. The finished winding is removed from the template after unscrewing the nut 8, removing the right disk and spreading the wedges 9 of the template. The machine is controlled by a pedal 10 connected to the clutch 5.


Rice. 125. Insulation of the magnetic circuit (a) and wedging of the windings (c) when installing the transformer windings:
1 - yoke insulation; 2 - a cylinder made of electric cardboard; 3 - round rods; 4 - slats; 5 - extension.

The windings are mounted on the rods of the magnetic circuit, previously tightly pulled together with a keeper tape (Fig. 125). The windings mounted on the magnetic circuit are wedged using beech strips and rods, having previously laid two layers of electric cardboard between the HV and LV windings. The beech strips rubbed with paraffin are first inserted between the wrappers to a depth of 30 - 40 mm, and then they are hammered alternately in opposite pairs (Fig. 125, b). To maintain the cylindrical shape of the windings, first round rods 3 are hammered, and then strips 4 with a hammer using a wooden extension 5, avoiding splitting the ends of the rods or strips.

In the same way, the LV winding is wedged on the rod with round wooden studs, hammering them around the entire circumference of the winding between the cylinder and the steps of the magnetic circuit rod.

After the end of the wedging of the windings, the upper yoke insulation is installed and the upper yoke of the magnetic circuit is charged.

In transformers of small power, for connecting windings with switch contacts and input rods, the ends of the wires are carefully stripped over a length of 15 - 30 mm (depending on their cross section), superimposed on each other, connected with a bracket of tinned copper tape 0.25 - 0 thick, 4 mm or a bandage of tinned copper wire 0.5 mm thick and soldered with POS-30 solder, using rosin or borax as a flux.

In high-power transformers, copper-phosphorus solder with a melting point of 715 ° C is used to connect the ends of the windings and attach them to the taps. The place of soldering is cleaned, insulated with paper and varnished cloth up to 25 mm wide and coated with GF-95 varnish. Winding taps are made with a damper at the end to protect the wire from breaking. The taps of the HV windings along the entire length are varnished GF-95.

The insulating parts of the transformer core are made of cardboard, paper, wood. These materials are hygroscopic and absorb moisture from the surrounding air, reducing their electrical insulating properties. For high electrical strength of the core insulation, it is dried in ovens in special cabinets, with a blower, etc.

The most commonly used in practice is the method of drying in its own heated tank: when an alternating current passes through a special winding superimposed on the insulated surface of the tank, a strong magnetic field is formed, which closes through the steel of the tank and heats it.

Dry the transformers in a tank without oil (to speed up the drying process of the active part and preserve the quality of the oil and winding insulation). The magnetizing winding placed on the tank heats the tank. The winding turns are placed on the tank in such a way that at least 60% of the winding is in the lower part of the tank. During warm-up, the tank lid is also insulated. The increase in temperature is controlled by changing the number of turns of the winding, while not allowing the temperature of the windings to rise above 100°C, and the temperature of the tank above 110-120°C.

The indicator of the end of drying is the steady value of the insulation resistance of the windings for 6 hours at a constant temperature not lower than 80°C. After drying is completed and the temperature of the windings decreases to 75-80 °C, the transformer tank is filled with dry oil.

Transformer tank repair

The inner surface of the tank is cleaned with a metal scraper and washed with used transformer oil. The dents are heated with a gas burner flame and straightened with hammer blows. Cracks on the edge and the wall of the body are welded by gas welding, and in the pipe - by electric welding. To check the quality of welding, the outer side of the seam is cleaned and covered with chalk, and moistened with kerosene from the inside (if there are cracks, the chalk is wetted with kerosene and darkens). The tightness of the body is checked by filling the tank with used oil for 1 hour at a temperature not lower than 10°C.

Before welding, cracks are drilled at its ends through holes a few millimeters in diameter. The edges of the crack are chamfered and welded by electric welding. The density of the seam is controlled using kerosene. Loose seams are cut out and welded again.

Extender repair

When repairing the expander, check the integrity of the glass tube of the oil indicator, the condition of the seals. The defective flat glass or glass tube of the oil indicator is replaced. Rubber gaskets and seals that have lost elasticity are replaced with new ones made of oil-resistant rubber. The sediment is removed from the bottom of the expander and washed with clean oil. The cork is rubbed with a fine abrasive powder. The gland packing is replaced with a new one, which is prepared from an asbestos cord soaked in a mixture of fat, paraffin and graphite powder.

Check the strength and tightness of the fastening of the glass diaphragm at the safety pipe; inner part pipes are cleaned of dirt and washed with clean transformer oil.

When repairing transformers, special attention is paid to the safety of insulators and the reinforcement of the bushings. Chips up to 3 cm² or scratches up to 0.5 mm deep are washed with acetone and covered with two layers of bakelite varnish, drying each layer in an oven at a temperature of 50 -60 ° C.

Repair of reinforcing seams

Reinforcement joints are repaired as follows: the damaged section of the joint is cleaned with a chisel and filled with a new cementing compound. If the reinforcing seam is destroyed by more than 30%, the bushing is completely replaced. The cementing composition per serving of one input is prepared from a mixture consisting (by weight) of 140 parts of magnesite, 70 parts of porcelain powder and 170 parts of magnesium chloride solution. This composition is used for 20 minutes. After the putty has cured, the seam is cleaned and coated with 624C nitro enamel.

Cleaning the thermosyphon filter

The thermosyphon filter is cleaned from the old sorbent, the internal cavity is washed with transformer oil, filled with a new absorbent and attached to the transformer tank on flanges.

Switch repair

Repair of the switch consists in the elimination of defects in the contact connections, insulating tubes of the cylinders and sealing devices. The contacts are cleaned, washed with acetone and transformer oil. Burnt and melted contacts are filed with a file. Broken and burnt contacts are replaced with new ones. Minor damage to the insulation of the tube or cylinder is restored with two layers of bakelite varnish. The weakened points of connection of the winding taps are soldered with POS-30 solder.

The repaired switch is assembled, the installation site is wiped with a rag, the gland seal is inspected, the switch handle is replaced and the studs are tightened. The quality of the switch is checked by switching its positions. Switching should be clear, and the locking pins in all positions should fully enter their sockets.

Checking the operation of a switching device for voltage regulation under load consists in determining the correct operation of the moving contacts in series. A And b switch and contactors K1 and K2. Violation of the sequence of operation of these elements of the switching device can lead to serious damage to the transformer and an accident in the electrical network.

Transformer assembly

The assembly of a transformer without an expander, the inputs of which are located on the walls of the tank, begins with lowering the active part into the tank, then the inputs are installed, the taps from the windings are connected to them and the switch, and the tank cover is installed. Small power transformer covers are installed on the lifting studs of the active part, completed with the necessary parts, and in more powerful ones, assembled separately. During assembly, the correct installation of sealing gaskets and the tightening of the fixing nuts are monitored. The length of the lifting studs is adjusted so that the removable part of the magnetic circuit and the cover are correctly positioned in their places. Pre-determine the required length of the lifting studs with a wooden lath. The length of the studs is adjusted by moving the nut.

The active part of the transformer with the help of lifting devices is lowered into the tank with a sealing gasket made of oil-resistant sheet rubber (Fig. 126).


Rice. 126. Gasket joint (a) and methods of installing the gasket (s) when sealing the tank with an oil-resistant rubber gasket:
1 - tank wall; 2 - limiter; 3 - tank cover; 4 - gasket; 5 - tank frame.

Brackets are installed on the tank cover for attaching an expander with an oil indicator, a safety pipe, a switch actuator, a gas relay and a blowout fuse.

The transformer is filled with dry transformer oil to the required level according to the oil indicator of the expander, the tightness of the fittings and parts is checked, as well as the absence of oil leakage from joints and seams.

TYPICAL TECHNOLOGICAL CARD

INSTALLATION OF POWER TRANSFORMERS WITH NATURAL OIL COOLING, VOLTAGE UP TO 35 kV, POWER UP TO 2500 kVA

1 AREA OF USE

A typical technological map has been developed for the installation of power transformers.

General information

Requirements for transportation, storage, as well as for installation and commissioning of power transformers are defined by the instruction "Transportation, storage, installation and commissioning of power transformers with voltage up to 35 kV inclusive without revision of their active parts" and guiding technical instructions "Power transformers, transportation , unloading, storage, installation and commissioning".

The power transformer, which arrived from the equipment supplier (manufacturer, intermediate base), is subjected to external inspection. During the inspection, they check the presence of all places according to the railway bill, the condition of the packaging, the absence of oil leaks at the joints of the radiators with the tank and in places of seals, the integrity of the seals, etc.

The packaging of dry transformers must ensure their safety from mechanical damage and direct exposure to moisture.

If a malfunction or damage is detected, an act is drawn up, which is sent to the plant or intermediate base.

After the inspection and acceptance of the transformer, they begin to unload it.

It is recommended to unload the transformer with a bridge or mobile crane or a stationary winch of the appropriate carrying capacity. In the absence of lifting means, it is allowed to unload the transformer onto the sleeper stand using hydraulic jacks. Unloading of transformer units (coolers, radiators, filters, etc.) is carried out by a crane with a lifting capacity of 3 to 5 tons. .

To lift the transformer, special hooks are provided on the walls of its tank, and eyelets (lifting rings) are provided on the roof of the tank. Slinging of cables for large transformers is carried out only by hooks, for small and medium ones - by hooks or eyelets. The poles and lifting ropes used for lifting must be made of a steel rope of a certain diameter, corresponding to the weight of the transformer. To avoid cable breaks, wooden linings are placed under all sharp edges of the bends.

The heavy-weight transformer arriving disassembled is unloaded using a heavy-duty railway crane. In the absence of such a crane, unloading is carried out using winches and jacks. To do this, the transformer tank installed on the railway platform is first lifted with two jacks by the lifting brackets welded to the bottom and walls of the tank, then a trolley supplied separately from the tank is brought under the tank, and with the help of winches the tank is rolled off the platform onto a specially prepared sleeper cage. Rolling is carried out along steel strips placed under the trolley rollers. The remaining components of the transformer (expansion tank, outlets, etc.) are unloaded with conventional cranes.

The unloaded transformer is transported to the installation site or to the workshop for revision. Depending on the mass of the transformer, transportation is carried out by car or on a heavy trailer. Carriage by dragging or on steel sheet is prohibited.

Vehicles used for the transportation of transformers must have a horizontal cargo platform that allows free installation of a transformer on it. When the transformer is located on the vehicle, the major axis of the transformer must coincide with the direction of travel. When installing a transformer on a vehicle, it is necessary to take into account the location of the inputs on the transformer in order to prevent a subsequent turn before installation at a substation.

Dismantled components and parts can be transported together with the transformer, if the carrying capacity of the vehicle allows and if the requirements for transportation of the transformer itself and its components are not violated.

The carrying capacity of the vehicle must not be less than the mass of the transformer and its elements in case of their transportation together with the transformer. It is not allowed to apply traction, braking or any other types of forces to the structural elements of the transformer during their transportation.

Figure 1 shows a diagram of the installation of a transformer on a car.

Fig.1. Scheme of installation and fastening of the transformer on the car

In some cases, prior to installation, transformers long time stored in on-site warehouses. Storage must be organized and carried out in such a way as to exclude the possibility of mechanical damage to transformers and dampening of the insulation of their windings. These requirements are met by certain storage conditions. Depending on the design and method of shipment of transformers, their storage conditions will be different. In all cases, it is necessary that the duration of storage of transformers does not exceed the maximum allowable established by the instructions mentioned above.

The storage conditions of power transformers with natural oil cooling are accepted according to the group of storage conditions of the OZHZ, i.e. in open areas.

Storage conditions for dry non-sealed transformers must comply with the conditions of group L, transformers with a non-combustible liquid dielectric - group OZH4. Storage conditions for spare parts (relays, fasteners, etc.) for all types of transformers must comply with condition group C.

Dry-type transformers must be stored in their own enclosures or original packaging and must be protected from direct exposure to atmospheric precipitation. Oil transformers and transformers with non-combustible liquid dielectric must be stored in their own tanks, hermetically sealed with temporary (during transportation and storage) plugs and filled with oil or liquid dielectric.

When storing transformers up to 35 kV inclusive, transported with oil without expanders, the installation of the expander and adding oil must be done as soon as possible. short term but not later than 6 months. When storing transformers with a voltage of 110 kV and above, transported without an expander with oil and without oil, the installation of the expander, topping up and filling with oil should be carried out as soon as possible, but no later than 3 months from the date of arrival of the transformer. The oil must comply with the requirements of the PUE. The oil level must be periodically monitored (when the level drops, it is necessary to add oil), at least once every 3 months it is necessary to take an oil sample for a reduced analysis. The absence of oil leakage from the transformer tank is checked periodically by traces on the tank and fittings. Sealed oil transformers and transformers with non-flammable liquid dielectric must be stored in the manufacturer's packaging and protected from direct precipitation.
2. ORGANIZATION AND TECHNOLOGY OF WORK PERFORMANCE


INSTALLATION OF POWER TRANSFORMERS WITH NATURAL OIL COOLING

The facilities mainly use power transformers with natural oil cooling, voltage up to 35 kV, power up to 2500 kVA. The scope of work for the installation of a power transformer with natural oil cooling depends on whether it comes from the factory - assembled or partially disassembled. Regardless of the type of delivery, the sequence of installation operations will be the same.

When installing a power transformer, it is necessary to perform the following operations in sequence:

Accept a room (installation site) and a transformer for installation;

Inspect the transformer;

Dry the windings (if necessary);

Assemble and install the transformer in place.

Acceptance for installation of a room (installation site) and a transformer

The room (open area) for the installation of the transformer must be completely completed by construction. Lifting devices or portals must be installed and tested prior to installation of the transformer.

As you know, the supply of power transformers and their delivery to the installation area must be carried out by the customer. When accepting transformers for installation and determining the possibility of further work, the whole range of issues related to transportation and storage, the condition of transformers for external inspection and determination of insulation characteristics, readiness and equipment of the room or installation site are considered.

The customer must submit the following required information and documents:

Date of dispatch of transformers from the manufacturer;

Conditions of transportation from the manufacturer (by rail or other transport, with or without oil, with or without expander);

The act of acceptance of the transformer and components from the railway;

Scheme of unloading and transportation from the railway to the installation site;

Storage conditions for transformers and component parts (oil level in the transformer, period for filling and topping up oil, characteristics of filled or topped-up oil, results of transformer insulation assessment, oil sample tests, leak tests, etc.).

At the same time, the condition of the transformer is assessed by external inspection, the results of the transformer tightness test and the condition of indicator silica gel.

During an external examination, they check for dents, the safety of the seals on the taps and plugs of the transformer.

The tightness of the transformer is checked before installation, before topping up or pouring oil. The seals must not be tightened before the tightness test. The tightness of transformers transported with an expander is determined within the limits of the oil indicator marks.

The tightness test of transformers transported with oil and a dismantled expander is carried out by pressure of an oil column 1.5 m high from the level of the cover for 3 hours. transformer. It is allowed to check the tightness of the transformer by creating an excess pressure of 0.15 kgf/cm (15 kPa) in the tank. The transformer is considered sealed if, after 3 hours, the pressure drops to no more than 0.13 kgf/cm (13 kPa). Checking the tightness of transformers transported without oil, filled with dry air or inert gas, is carried out by creating an excess pressure of 0.25 kgf / cm (25 kPa) in the tank. The transformer is considered sealed if the pressure drops after 6 hours to no more than 0.21 kgf / cm (21 kPa) at a temperature environment 10-15 °С. The creation of excess pressure in the transformer tank is carried out by pumping dry air through a silica gel dryer with a compressor or by supplying dry inert gas (nitrogen) from cylinders to the tank.

Acceptance of transformers for installation is documented by an act of the established form. Representatives of the customer, assembly and commissioning (for transformers of size IV and above) organizations participate in the acceptance.

revision

An audit of power transformers is carried out before installation in order to check their condition, identify and timely eliminate possible defects and damage. The audit can be carried out without inspection of the removable (active) part or with its inspection. All transformers subject to installation are subject to audits without inspection of the removable part. An audit with an inspection of the withdrawable part is carried out in cases of detection of damage to the transformer, which cause assumptions about the presence of internal faults.

Transformers currently produced have additional devices that protect their removable part from damage during transportation. This makes it possible, under certain conditions of storage and transportation, not to carry out a laborious and expensive operation - an audit with a lift of the removable part. The decision to install transformers without revision of the withdrawable part should be made on the basis of the requirements of the instructions "Transportation, storage, installation and commissioning of power transformers for voltage up to 35 kV inclusive without revision of their active parts" and "Power transformers. Transportation, unloading, storage, installation and commissioning. At the same time, a comprehensive assessment of the fulfillment of the requirements of the instructions is carried out with the execution of the relevant protocols. If the requirements of the instructions are not met or faults are detected during external inspection that cannot be eliminated without opening the tank, the transformer is subject to revision with an inspection of the removable part.

When carrying out an audit without inspecting the removable part, a thorough external examination of the transformer is carried out, an oil sample is taken for dielectric strength testing and chemical analysis; measure the insulation resistance of the windings.

During the inspection, check the condition of the insulators, make sure that there are no oil leaks at the seals and through the welds, that the required oil level is present in the expander.

The electric strength of the oil, determined in a standard vessel, should not be less than 25 kV for devices with higher voltage up to 15 kV inclusive, 30 kV for devices up to 35 kV and 40 kV for devices with voltage from 110 to 220 kV inclusive.

Chemical analysis of transformer oil is carried out in a special laboratory, and the compliance of the chemical composition of the oil with the requirements of GOST is determined.

The insulation resistance of the windings is measured with a megaohmmeter for a voltage of 2500 V. The insulation resistance is measured between the windings of higher and lower voltages, between each of the windings and the housing. For oil transformers with higher voltage up to 35 kV inclusive and power up to 6300 kVA inclusive, insulation resistance values ​​measured at the sixtieth second () must be at least 450 MΩ at +10 °C, 300 MΩ at +20 °C, 200 MΩ at +30 °C, 130 MΩ at +40 °C. The value of the absorption coefficient must be at least 1.3 for transformers with a power of up to 6300 kVA inclusive.

The physical essence of the absorption coefficient is as follows. The nature of the change in the measured value of the winding insulation resistance over time depends on its condition, in particular, on the degree of moisture. To understand the essence of this phenomenon, we use the equivalent circuit of the winding insulation.

Figure 2 shows the insulation resistance measurement circuit and the equivalent circuit. In the process of measuring the insulation resistance with a megohmmeter, a DC voltage is applied to the insulation of the winding. The drier the winding insulation, the greater the capacitance of the capacitor formed by the winding conductors and the transformer case, and therefore, the greater the charge current of this capacitor will flow in the initial measurement period (at the fifteenth second from the moment the voltage is applied) and the megohmmeter readings will be smaller ( ). In the next measurement period (at the sixtieth second), the capacitor charge ends, the charge current decreases, and the megohmmeter reading increases () . The drier the insulation of the windings, the greater the difference in the readings of the megohmmeter in the initial () and final () periods of measurement and, conversely, the wetter the insulation of the transformer windings, the smaller the difference in these readings.

6. TECHNICAL AND ECONOMIC INDICATORS

State budget standards.
Federal unit prices for equipment installation.
Part 8. Electrical installations
FERM 81-03-08-2001

Order of the Ministry of Regional Development of Russia dated 04.08.2009 N 321

Table 08-01-001. Power transformers and autotransformers

Meter: pcs.


Price code

Name and technical specifications equipment or types of mounting

Direct costs, rub.

Including, rub.

Labor costs of workers -
installers, man-hour

Wages of workers
installers

machine operation

mate-
rials

Total

including the wages of the workers who operate the machine

Three-phase transformer:

08-01-001-06

35 kV with a capacity of 2500 kVA

7018,51

2635,88

3748,71

360,72

633,92

274

BIBLIOGRAPHY

SNiP 3.03.01-87. Bearing and enclosing structures.

SNiP 12-03-2001. Labor safety in construction. Part 1. General requirements.

SNiP 12-04-2002. Labor safety in construction. Part 2. Construction production.

GOST 12.2.003-91. SSBT. Production equipment. General safety requirements.

GOST 12.3.009-76. SSBT. Loading and unloading works. General safety requirements.

GOST 12.3.033-84. SSBT. construction machines. General safety requirements for operation.

GOST 24258-88. Scaffolding tools. Are common specifications.

PPB 01-03. Rules fire safety V Russian Federation.

The electronic text of the document was prepared by CJSC "Kodeks"
and verified according to the author's material.
Author: Demyanov A.A. - Ph.D., teacher
Military Engineering and Technical University,
St. Petersburg, 2009

Maintenance transformers with a capacity of 10000 - 63000 kV-A 1. The composition of the performers

Electromechanic - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

Preparatory work and permission to work

4.1. On the eve of the work, apply for the withdrawal of the trans for repair
formatter.

4.2. Check the serviceability and expiration dates of protective equipment, devices
ditch, prepare tools, mounting fixtures and materials.

4.3. After issuing an order to the work foreman, receive instructions from
the person who issued the order.

4.4. Operational personnel to prepare the workplace.
For the foreman to check the implementation of technical measures for
workplace preparation.

4.5. Get the team to work.

4.6. The foreman to instruct the members of the brigade and clearly
distribute responsibilities among them.


End of technological card No. 2.2.

Oil change in hydraulic seals of oil-filled bushings A silica gel in moisture-absorbing cartridges (see fig. 2.1.1 ., fig. 2. 1 .3.) The condition of the silica gel in the desiccant cartridges is determined by the color of the indicator silica gel. If the color changes from blue to pink, replace the silica gel in the cartridges and the oil in the water seal. Replace Siliga gel in dry weather, taking the dryer out of operation for no more than one hour. Check the oil level in the hydraulic seal. The replacement of silica gel is carried out as follows: disconnect the cartridge from the input, replace the silica gel, having previously cleaned the cartridge of contamination, change the oil in the hydraulic seal, attach the cartridge to the input
Checking the working condition of the cranes and dampers of the transformer Check the compliance with the working position of devices, valves, dampers. Carry out an inspection with checking the oil level in the bushings and tanks of the transformer. Record readings of thermal alarms, oil level indicators, air temperature, position of switches of all windings

Note. All operations with oil filled and 110-220 kV bushings must be carried out in cooperation with a RRU specialist.



Completion of works


Technological map No. 2.3. Current repair of autotransformers for voltage 110-220 kV

Cast

Electromechanic - 1

Traction substation electrician 4th category - 1

Traction substation electrician 3rd category - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Safety helmets, safety belt, ladder, grounding, shorts, dielectric gloves, megohmmeter for voltage 1000 and 2500 V, stopwatch, thermometer, level, pump with pressure gauge and hose, wrenches, combination pliers, screwdrivers, scraper, brushes, container for draining sediment, glass containers with a ground stopper for oil sampling, indicator silica gel, silica gel, transformer oil, TsIA-TIM lubricant, white spirit, moisture-oil-resistant varnish or enamel, spare oil-indicating glasses, rubber gaskets, cleaning material, rag

Technological map No. 2.4. Current repair of transformers with a capacity of 40 - 630 kV-A

Cast

Electromechanic - 1

Traction substation electrician 3rd category - 1

Terms of work

The work is being done:



2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Safety helmets, safety belt, ladder, grounding, shorts, dielectric gloves, megohmmeter for voltage 1000 and 2500 V, stopwatch, thermometer, level, pump with pressure gauge and hose, wrenches, combination pliers, screwdrivers, scraper, brushes, container for draining sediment, glass containers with a ground stopper for oil sampling, indicator silica gel, silica gel, zeolite, transformer oil, CIATIM lubricant, white spirit, moisture-oil-resistant varnish or enamel, spare oil-indicating glasses, rubber gaskets, cleaning material, rag

Oil circuit breakers


Continuation of technological map No. 3.1.

Cast

Electromechanic - 1

Traction substation electrician 4 categories - 1 Traction substation electrician 3 categories - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Safety helmets, safety belt, ladder, grounding, short circuits, dielectric gloves, megohmmeter for voltage 1000 and 2500 V, electric stopwatch, wrenches, combined pliers, screwdrivers, scraper, brushes, glass containers with a ground stopper for oil sampling, silica gel indicator, silica gel, transformer oil, CIATIM grease, white spirit, insulating varnish, spare oil-indicating glasses, rubber gaskets, cleaning material, rags

Cast

Electromechanic - 1

Traction substation electrician 3rd category - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Protective helmets, safety belt, ladder, grounding, short circuits, dielectric gloves, megohmmeter for voltage 1000 and 2500 V, LVI-100 test facility, electric stopwatch, wrenches, combined pliers, screwdrivers, scraper, brushes, transformer oil, CIATIM lubricant, white spirit, insulating varnish, spare oil-indicating glasses, rubber gaskets, cleaning material, rags

Completion of works

6.1. Collect instruments, tools, fixtures and materials.

6.2. Return to the switchboard traction substation.

6.3. Pass workplace admitting and close the outfit

6.4. Record the results of the measurements taken in a protocol.


Cast

Electromechanic - 1

Traction substation electrician 3rd category - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Protective helmets, grounding, short circuits, dielectric gloves, megohmmeter for voltage 1000 and 2500 V, electric stopwatch, wrenches, combination pliers, screwdrivers, scraper, transformer oil, TsIA-TIM grease, white spirit, insulating varnish, spare oil-indicating glasses, rubber pads, cleaning material, rags

Completion of works

6.1. Collect instruments, tools, fixtures and materials.

6.2. Return to the switchboard traction substation.

6.3. Hand over the workplace to the admitting and close the outfit

6.4. Record the results of the measurements taken in a protocol.


Cast

Electromechanic - 1

Traction substation electrician 4th category - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Megaohmmeter for voltage 500 and 2500 V, tester, electric soldering iron, vacuum cleaner, calibration wrench, wrenches, combined pliers, screwdrivers, files, scraper, control lamp, hair brush, wooden ladder, ladder, white spirit, cleaning material, CIATIM lubricant

Completion of works

6.1. Collect instruments, tools, fixtures and materials.

6.2. Return to the switchboard traction substation.

6.3. Hand over the workplace to the admitting and close the outfit

6.4. Record the results of the measurements taken in a protocol.


Cast

Electromechanic - 1

Traction substation electrician 4th category - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Ohmmeter, portable lamp, vacuum cleaner, wrenches and socket wrenches, screwdrivers, ruler, caliper, files, scraper, wire brush, set of probes, files for cleaning switch contacts, wooden stick, sandpaper, white and carbon paper, white spirit, lubricant CIATIM, rags, cleaning material

Cast

Electromechanic - 1

Traction substation electrician 4th category - 1

Terms of work

The work is being done:

2.1. With stress relief

2.2. Alongside

3. Protective equipment, devices, tools, fixtures and materials:

Stopwatch, portable lamp, vacuum cleaner, wrenches and socket wrenches, screwdrivers, ruler, caliper, files, scraper, wire brush, set of probes, files for cleaning switch contacts, glass cloth, wooden stick, sandpaper, white and carbon paper, white spirit, TsIA-TIM lubricant, rags, cleaning material

Transformers Technological map No. 2.1.

Removing the transformer from the electric locomotive (work is done after removing the small removable roof and cooling fans of the traction transformer)

1.1 Disconnect all shunts and busbars from the traction transformer, stage switch and instrument cabinet.

1.2 Disconnect the cables and low-voltage wires from the substation and the instrument cabinet, having previously checked their marking. If there is no marking, restore, if the marking is incorrect, re-mark.

1.3 Loosen the bolts securing the transformer to the frame of the locomotive body. Remove fence nets.

1.4 Moor the traction transformer with a 30-ton overhead crane and move it to the transformer compartment on a transport trolley

Preliminary tests of the transformer.

2.1 Install the transformer in the test station

2.2 Measure the insulation resistance of all windings in accordance with clause 11.2.1.

2.3 Measure the ohmic resistance of the windings in accordance with clause 11.2.2.

2.4 Test the dielectric strength of the winding insulation in accordance with clause 11.2.4.

2.5 Make experience x.x. similarly to clause 11.2.6.: at a voltage of 62.5 V, the losses should not exceed 2.3 kW.

When testing, set possible faults and determine the extent of the repair. If necessary, repair the active part.

Disassembly of the traction transformer.

3.1 Place the transformer in the repair position

3.2 Clean the traction transformer from dirt and dust.

3.3 Drain the oil from the traction transformer, stage switch and expansion tank.

3.3 Remove the substation, instrument cabinet and oil pumps from the transformer and transfer them for repair.

3.4 Remove BF50/10 gas switch, air dryer, flow meters, thermostats and expansion tank.

3.5 Remove the separating plate.

3.6. Remove assembly hatch covers, disconnect current transformers, inputs.

3.7 Remove bushings m1-m4.

3.8 Loosen the bolts securing the bell to the transformer tank.

3.9 Moor with an overhead crane and remove the bell.

3.10. Dismantle the cooling system.

Repair of the active part of the transformer (magnetic circuit and windings).

4.1 Check the condition of the insulation of the accessible turns of the coils, leads, contamination of the surfaces of the windings, the magnetic circuit and the leads with oil deposits, as well as the dimensions of the cooling channels.

4.2 Check the condition of the fastening, wedging and compression of the windings, the condition and fastening of the insulating gaskets between the coils, the serviceability of the electrical connections, the absence of overheating, overlaps, the absence of deformations and displacements of the coils and gaskets.

4.3 Loose fastening of the windings should be restored by tightening the pressure bolts or placing wedging inserts made of getinax between the pressure plate and the yoke sheets. Tighten the pressure bolts with a torque wrench with a torque of 12-13 kg / cm. After tightening the bolts, cotter with wire.

4.4 Tighten the bolts at the bottom of the tie-down frame on both sides of the bottom of the tank. If necessary, install a fiberglass gasket between the tie-down frame and the magnetic circuit. The tightening torque of the bolts should be 5-6 kg/cm.

4.5 Bulging winding coils in the absence of open circuits, interturn short circuits and satisfactory insulation resistance relative to the body and other windings, it is allowed to fill in the original position with light hammer blows through a wooden gasket.

4.6 Check the insulation resistance of the tie rods with respect to the magnetic circuit with a 1000 V megger.

4.7. Check the serviceability of the grounding of the magnetic circuit, the serviceability of the fastening of the grounding shunt between the sheets of the magnetic circuit, the absence of traces of heating and melting of the shunt and iron of the magnetic circuit.

4.8 Clean the contacts of the 25/12kV switch, check their pressing and fit, check the fastening of the cables, set the switch to the “25kV” position.

4.9 Clean the insulating plates of the autotransformer terminals and the secondary windings of the transformer from dirt, degrease, inspect, replace the defective ones.

4.10 Inspect the current transformers, check the fastening, the integrity of the windings, the absence of cracks, melting and other damage.

4.11 Remove the inlets on the tank cover, clean, inspect, replace the seals. Replace cracked bushings. It is allowed to repair bushings D25, D1 type Kkr37 / 63O according to the manufacturer's technology in accordance with the Rules for the care of the transformer kit.

4.12 Remove oil deposits from the surfaces of the windings, terminals, magnetic circuit and from the cooling channels. Use of wooden scrapers is allowed. Rinse the transformer with clean, dry transformer oil.

4.13 Clean the transformer tank, expander and cooling system from sludge and sediment, rinse with clean warm dry transformer oil. Clean the outer part of the coolers from dust and dirt, degrease with gasoline.

4.14 Inspect the inner walls of the tank and its roof, check the color strength of the inner surface. Sand the areas with peeling paint and paint with epoxy ester primer. Check the condition of welding of the installation chambers inside the tank for installing the magnetic rod, the serviceability of the felt pads under the paws of the magnetic rod, and the devices for attaching the core to the tank.

4.15 Check the condition of oil pipelines, their valves, valves and seals, replace or repair defective ones. Inspect welds, cut out defective ones and repair.

4.16 The active part of the transformer must be in the air for no more than 24 hours at an air humidity of not more than 75%.

Repair of transformer cooling radiators.

5.1 Prepare radiators for testing. Install clamps to prevent deformation. Assemble the compressed air flange. Close the opposite flange tightly.

5.2 Connect the pressure hose with pressure reducing valve to the radiator flange.

5.3 Immerse the radiators in a tank with water heated to 60 0 С.

5.4 Test the radiators with an air pressure of 2.5 atm.

5.5 Dismantle test devices on serviceable radiators. Rinse radiators with transformer oil and hand over for assembly.

5.6 Remove the defective radiator from the radiator set. Install the blind flange on the radiator. Immerse the radiator in a tank with water heated to 60 0 C and test individual pipes with an air pressure of 2.5 atm. Mark the places of defects. Remove the radiator from the fixture and seal the defective pipes tightly on both sides with tin. In one radiator, it is allowed to close up no more than 5% of the tubes.

5.7 After repair, assemble a set of radiators and repeat the tests in paragraphs 5.1.-5.5.

Drying of the transformer windings is carried out when the insulation resistance of the windings is below the standard values ​​or when the active part is in the air for more than 24 hours.

6.1 Move the transformer to the drying cabinet.

6.2 Turn on the cabinet heating and, with the cabinet lid ajar, heat the transformer to a temperature of 85-95 0 С with a temperature rise rate of not more than 60 0 С/hour.

The temperature is controlled by thermoelements installed at 2 points: on one of the coils at the top between the insulation cuffs and on the plate for the magnetic circuit coupler.

6.3 After reaching the transformer temperature of 85-95 0 C, close the cabinet and dry the transformer in a vacuum. The increase in vacuum is not more than 0.25 atm/hour (0.025 MPa/hour).

After reaching a vacuum of 0.00665-0.000133 atm. (665-13.3 Pa) dry for 28 hours. at a temperature of 85-95 C.

With TR-3, drying is allowed at a vacuum of at least 5320 Pa (0.0532 atm).

6.4 The end of drying is the moment when the insulation resistance of the windings exceeds the standard values ​​and practically stops increasing. The condensate outlet should be no more than 0.5 l/h.

6.5. At the end of drying, stop heating and eliminate the vacuum at a rate of not more than 0.01875 MPa/hour (0.1875 atm/hour).

6.6 After drying, tighten the fastening of the windings with pressure bolts with a torque of 12-13 kgf / m, if necessary, put a gasket made of getinax between the pressure plate and the magnetic circuit. Tighten and cotter the connecting bolts, tubes, holders.

6.7 Check the condition of the insulation of the tie rods of the magnetic circuit with a 1000 V megger.

6.8 Move the transformer to the assembly tank.

6.9 With TR-3, it is allowed to dry the transformer in its own tank by short-circuiting the traction winding. Short circuit current should not be more than half the rated current of the traction winding.

Transformer assembly.

7.1 Check the insulation resistance of the windings relative to each other and relative to the housing:

high-voltage winding (Do, D1, D25) - 100 MΩ;

traction windings (m1-m4) - 20 MΩ;

heating winding (C1-C2) - 10 MΩ;

auxiliary winding (E-J) - 5 MΩ.

7.2 Assemble the tank: cooling system, inlets, insulating plates, stage switch, 25/12.5 switch, current transformers, assembly hole covers, expansion tank.

When assembling, install new seals made of oil-resistant rubber.

7.3 Fill the transformer with oil.

Open one uppermost air outlet. Fill the tank from the bottom side with dry warm transformer oil, heated to 70 0 С.

When the transformer temperature is less than 60 0 C, it is necessary to heat the transformer by circulating warm oil between the transformer and the filter device until the temperature of the transformer and oil is equal. For heating, set the circulation rate to 450-600 l/h for 7 hours.

7.4 After installing the BF50/10 gas relay and air dryer, fill the transformer with oil through the expansion tank.

7.5 Bleed air from the tank at 12 points.

7.6 Bleed oil with pumps for 2 hours, then bleed air again at 12 points.

7.7 Leave the transformer for 2 days, then bleed the air at 12 points.

Air dryer repair.

8.1 Dismantle the air dryer removed from the transformer.

8.2 Inspect the parts of the air dryer, replace the unusable ones.

8.3 Regenerate the drying agent.

Pour the drying agent into a clean lining with a layer of no more than 10 mm.

Heat the drying agent in the drying chamber and dry at a temperature of 120-180 0 C for 3 hours.

The end of drying is a change in color from pink to bright blue.

The brown color of the color indicates the destruction of the drying properties as a result of overheating.

Drying agent can be regenerated up to 50 times

8.4 Assemble the air dryer. The oil seal must be transparent.

Fill the air dryer space with a mixture of 80% silica gel ( white color) and 20% blaugel (bright blue).

8.5.Install the air dryer on the expansion tank and fill the oil seal of the air dryer with transformer oil up to the level indicated by the mark on the oil seal.

Repair of gas relay BF50/10/

9.1. To remove the relay from the transformer, after draining the oil from the transformer, unscrew the outlet bolt in the lower part of the relay housing and drain the oil, disconnect the control circuit wires from the terminal rail, disconnect the grounding shunt and remove the relay.

9.2 Remove the internal mechanism from the housing, carefully inspect, eliminate defects, assemble the relay.

9.3 Test the dielectric strength of the insulation of the electrical circuits of the relay relative to the housing with and without transformer oil.

The test is carried out with an alternating voltage of 2.5 kV with a frequency of 50 Hz for 5 seconds.

9.4 Check the relay for tightness.

The check should be carried out within 20 min. With an excess oil pressure of 1 kgf / cm 2, there should not be a drop in oil pressure, observed on the stand pressure gauge, and there should be no oil leakage from the relay.

9.5 Carry out a functional test of the relay.

9.5.1 Carry out a triple control of the operation using the control button on the relay filled with oil.

In this case, the signal lamp of the stand should work.

9.5.2 Check the operation of the relay when the oil level drops.

Inflate air through the control cock. In this case, the signal lamp of the stand should work.

Drain the oil from the relay. In this case, two signal lamps of the stand should work.

9.6 Test results according to paragraphs 9.3.-9.5. put in a journal.

9.7 Put a working relay on the transformer and connect the wires of the control circuits to the terminal rail in accordance with the diagram.

Testing thermostats.

10.1 Install the thermostat in a bath with transformer oil heated to 60-80 0 C and a control thermometer placed in it.

10.2 Set the thermostat to the maximum temperature (110 0 C).

10.3 Connect to thermostat terminals 1,3 electrical circuit thermostat activation signaling.

10.4. Gradually reduce the temperature of the thermostat setpoint until the alarm is triggered to turn on the thermostat.

10.5. Compare the readings of the control thermometer with the readings of the thermostat scale.

10.6. If the readings of the thermostat and the control thermometer coincide, install the thermostat on the transformer tank.

10.7 If the readings do not match, adjust the thermostat.

Use a screwdriver to fix the adjusting axle. Loosen the set screw. While holding the axis, set the scale with the mark to the actual temperature at which the thermostat should have worked. Fasten the set screw.

10.8 After adjustment, test the thermostat again according to paragraphs 10.1.-10.5.

10.9 Connect the wires of the control circuits to the terminals of the thermostats according to the wiring diagram.

10.10 Adjust thermostat settings:

01513 - setting 80 0 C;

01525 - setting 40 0 ​​C;

01526 - setting 60 0 C;

01529 - setting 20 0 С.

Traction transformer tests.

Transformer testing after SR.

Transformer tests after TR-3.

11.1 Preparatory operations.

11.1.1 Ground the transformer case.

11.1.2 Turn on the oil pumps and pump oil for 2 hours.

Settle the oil for 12 hours.

11.1.3 Perform an oil analysis in accordance with the Instructions for the use of lubricants on locomotives and MVPS TsT-2635.

11.1.4 Release air from insulators, radiators, gas relay, voltage switch.

11.1.5 Check the operation of the PS oil filtration pump, PS oil heating system.

11.1.6 Check the polarity of the winding protection current transformers high voltage and the correctness of the circuit in the terminal box. Ring current transformers of traction windings and heating windings.

11.1.7 Short-circuit and ground all current transformers.

11.2.1 Measure the insulation resistance of all windings relative to the housing and relative to each other with a 2500 V megger.

The insulation resistance must be at least:

  • high-voltage winding - 100 MΩ;
  • heating winding - 10 MΩ;
  • traction windings - 20 MΩ;
  • winding of own needs - 5 MΩ.

Determine the absorption coefficient (moisture content of the windings)

K \u003d R60 / R15\u003e 1,

At a measurement temperature above 15 0 C, recalculate by multiplying the readings by a coefficient from the table

temperature difference 5 0 С 10 0 С 15 0 С 20 0 C 25 0 C 30 0 С
Coefficient 1,23 1,5 1,64 2,25 2,75 3,4

11.2.2 Measure the ohmic resistance of the windings using a voltmeter-ammeter or a DC bridge.

Check the resistance of the autotransformer winding at all positions.

The resistance values ​​should not differ from the nominal ones by more than 10%.

Nominal values ​​of winding resistance, MOhm

m1-m2 m3-m4 E-J E-H E-G E-F C1-C2 Do-D25 Do-D1
1,6 1,6 1,1 0,8 0,66 0,42 46 492 460

Autotransformer winding resistance by position, mΩ

Pos. Resist. Pos. Resist. Pos. Resist. Pos. Resist.
Do-1 19,2 Do-9 98,4 Do-17 210,0 Do-25 364,0

Resistance of coils of autotransformer winding, Ohm

Cat. Resist. Cat. Resist. Cat. Resist. Cat. Resist.
1 0,0182 4 0,0080 7 0,0086 10 0,0104

At an ambient temperature that differs from 15 0 C, it is necessary to bring the resistance to 15 0 C according to the formula:

R 15 \u003d R env - , where

R okr - winding resistance at ambient temperature

environment, Ohm;

t env - ambient temperature, 0 С.

11.2.3 Checking the transformation ratio.

Apply to the high voltage winding by placing a jumper Do-PS, voltage 200 V.

Measure voltages at all positions of the autotransformer winding and at all other windings with the PS position at 32 pos.

Voltage values ​​must correspond to those indicated in the table

conclusions Do-D m1-m2 m3-m4 C1-C2 E-F E-G E-H E-J
Voltage, V 200 8,3 8,3 24,7 1,1 1,8 2,1 2,8
NN For example, in NN For example, in NN For example, in NN For example, in
1 7,4 9 42,8 17 82,3 25 142,8

11.2.4 Testing the dielectric strength of the winding insulation relative to each other and relative to the housing with a voltage of 50 Hz for 1 min.

Test voltage values:

  • HV winding 25 kV (Do, D1, D25) - 52.5 kV;
  • heating winding (C1, C2) - 11.2 kV;
  • traction windings (m1-m2, m3-m4) - 4.9 kV;
  • auxiliary winding (E-J) - 1.54 kV.

The test voltage is applied between the short-circuited winding to be tested and the earthed tank to which all other short-circuited transformer windings are connected.

The transformer is considered to have passed the test if no breakdown or partial discharges were observed during the tests, determined by sound, gas, smoke or instrument readings.

11.2.5 Test of dielectric strength of insulation by induced voltage with double rated voltage of increased frequency of 200 Hz for 30 sec. The test checks the turn insulation of the transformer windings.

A voltage of 2080 V is applied to the terminals m3-m4 of the traction winding, the remaining windings are open, while one output of each winding (Do, E, C1, m1) is grounded.

The transformer is considered to have passed the test, if during the tests there were no current surges, no smoke from the expander.

11.2.6 Idling experience.

Measure losses and no-load current, while checking the condition of the magnetic system of the transformer. Connect the rated voltage to the m3-m4 winding, and then 115% of the rated voltage with a frequency of 50 Hz. All

the remaining windings are open, one terminal of each winding is grounded.

The following values ​​of losses and current x.x are allowed.

Uxx=1040 V Ixx=90-120 A Pxx=94-125 kW

Uxx=1200 V Ixx=100-140 A Pxx=120-168 kW

11.2.7 Short circuit test.

Apply a voltage of 200 V with a frequency of 50 Hz to the Do-D25 winding. The low-voltage windings are short-circuited in turn, and the current, voltage and short-circuit power are measured.

Measured short-circuit losses convert to nominal values:

Рн=Рism*K1*K2, where

Rism — measured short-circuit losses, kW;

К1=Uн/Umeas — voltage conversion factor;

К2=In/Imeas — current conversion factor.

By comparing the measured values, reduced to the nominal mode, with the permissible ones, check the correctness of the windings.

When shorting the traction windings, simultaneously check the current transformers protecting the traction windings. When short-circuiting the heating winding, check the current transformers protecting the heating winding.

Shorted pins Transformer terminals K=Iobm/Itransf
m1-m2 836-837 80

11.2.8 Check the insulation resistance of all windings as in paragraph 11.2.1.

11.3.1 Measurement of winding insulation resistance according to clause 11.2.1.

11.3.2 Measurement of the ohmic resistance of the windings according to clause 11.2.2.

11.3.3 Testing the electrical strength of the winding insulation according to clause 11.2.4.

11.3.4 Idling test according to item 11.2.6.

Coloring of external surfaces of the transformer.

12.1 Paint the cooling system with PF-115 enamel yellow color at least 2 times.

12.2 Paint the transformer with PF-115 gray enamel at least 2 times.

12.3 Paint the underbody part of the transformer with black enamel.

Delivery of the transformer to the receiver of locomotives.

13.1 Fill in the transformer test report.

13.2 Together with the workshop foreman, present the transformer for delivery to the locomotive receiver.

Up